Nevada Supreme Court Decides Enforceability of Contractual Lien Waiver Provisions
The Nevada Supreme Court recently addressed two issues of concern to
contractors and owners: (1) the enforceability of lien waiver
provisions, and (2) the enforceability of pay-if-paid provisions. Lehrer McGovern Bovis, Inc. v. Bullock Insulation, Inc.,
124 Nev. Adv. Op. 39 (June 2008), is the latest saga from the Venetian
mechanics' lien lawsuits. The case involved the owner and general
contractor attempting to foil a subcontractor's lien foreclosure and
breach of contract claims by asserting a lien waiver provision and a
pay-if-paid provision in the subcontract agreement. The
Court declared that Nevada's public policy "favor[s] contractors'
rights to secured payment for labor, materials, and equipment
furnished." Based on this policy, the Court struck down both the lien
waiver provision and the pay-if-paid provision. The subcontract
agreement at issue predated the legislative amendments to the
mechanics' lien statutes, NRS Chapter 108, requiring specific forms for
lien waivers and predated the amendments to NRS Chapter 624, which
created Nevada's prompt payment statutes. Although not at issue, the
Court thought it necessary to state, without explanation or analysis in
what will become known as the infamous Footnote 33, that the amendments
to Chapter 624 creating the prompt pay statutes, "make pay-if-paid
provisions entered into subsequent to the Legislature's amendments
unenforceable."
Mechanics' Lien Waivers
The
subcontract agreement between subcontractor Bullock Insulation and
general contractor Bovis incorporated a provision from the general
conditions in which Bullock Insulation promised "'not [to] suffer or
permit any lien or other encumbrance to be filed' against the project."
The Court noted that the "lien waiver provision applies regardless of
whether Bullock Insulation received any payment" and therefore
concluded that "such provision violates public policy, as it fails to
secure payment for Bullock Insulation."
The Court assured that
not every lien waiver provision violates public policy and that the
enforceability of a lien waiver clause must be decided on a
case-by-case basis. Limiting the enforceability of lien waiver
provisions to the facts of each case seems like a fair result, but the
Court gave no guidance as to what types of lien waiver provisions would
be enforceable without payment in full. The public policy proclamation
coupled with NRS 108.2453(1), which prohibits the waiver of mechanics'
lien rights unless the appropriate forms specified in Chapter 108 are
completed and payment made, suggest that without payment in full,
mechanics' lien rights can not be waived.
Pay-If-Paid Provisions
More
disturbing than the Court's treatment of the lien waiver provision is
its decision on the pay-if-paid provision. The subcontract agreement
contained a pay-if-paid provision whereby Bullock Insulation's right to
payment for its work was contingent upon payment by the owner to Bovis.
The Court held the provision unenforceable because "a pay-if-paid
provision limits a subcontractor's ability to be paid for work already
performed" and therefore "such a provision impairs the subcontractor's
statutory right to place a mechanic's lien on the construction
project." Rather than limit the holding to a case-by-case analysis,
however, the Court concluded that all pay-if-paid provisions that were
entered into before the amendments to NRS Chapter 624 are unenforceable.
What's more, in Footnote 33, the Court proclaimed,
We note that in 2001, the Legislature amended NRS Chapter 624 to include prompt payment provisions contained in NRS 624.624 through 624.626, which make pay-if-paid provisions entered into subsequent to the Legislature's amendments unenforceable. (emphasis added).
The
Court acknowledged that the amendment to Chapter 624 "does not affect
our analysis here because it is not retroactive." Yet, the Court rang
the bell anyway.
A major problem with Footnote 33 is that the
prompt payment statutes in Chapter 624 do not render pay-if-paid
clauses unenforceable. In fact, NRS 624.626(1)(b) recognizes that
pay-if-paid or pay-when-paid provisions regularly exist in subcontract
agreements and grants the subcontractor the remedy of stopping work
when a higher-tiered contractor does not timely pay a lower-tiered
contractor even if the higher-tiered contractor has not been paid by
the owner. Additionally, pay-if-paid provisions do not necessarily
eliminate a subcontractor's mechanic's lien rights. Even with a
pay-if-paid provision in a subcontract agreement, the subcontractor
remains able perfect and foreclose on its mechanic's lien against the
owner. Despite these remedies, Footnote 33 effectively makes the
general contractor a lender of the owner by requiring general
contractors to pay subcontractors when the general has not received
payment from the owner. This is true even if the subcontractor has
assumed the risk of nonpayment by agreeing to a pay-if-paid provision.
Where To Go From Here
Undoubtedly, the Bovis
decision will draw a lot of criticism. A motion for rehearing would not
be surprising. The decision makes it more important than ever for
general contractors to verify the financial viability of owners to
complete a project. So far, the decision appears favorable to
subcontractors that are subject to now-unenforceable lien waiver and
pay-if-paid provisions. Owners should expect post-Bovis
contracts to attempt to allocate more heavily to the owner the general
contractor's risk of liability to subcontractors for owner nonpayment.
But even a reallocation of risk cannot protect a general contractor
from an insolvent owner.
Email Post
| Categories: Construction | Lien | Nevada | Waiver
