Construction Law Blogtag:www.fclaw.com,2009:/construction-law/blog/Setting the Standard for Construction Law in the SouthwestMango 1.2.2CASE ALERT—New Arizona Appellate Decision Enforces Narrow Form Indemnity Clause Against General Contractorurn:uuid:D5BC8559-1422-1360-CC20AF6A0523B96D2008-11-25T03:11:00Z2008-11-25T03:11:00Z<p>On November 13, 2008, the Arizona Court of Appeals issued its decision in <em>MT Builders, LLC v. Fisher Roofing, Inc.</em>, interpreting a “narrow form” subcontract indemnity provision which reads, in part as follows: “the [Subcontractor] shall indemnify and hold harmless [General Contractor] ... from and against all claims . . . arising out of [Subcontractor’s] work . . . <strong><em>to the extent</em></strong> caused in whole or in part by any negligent act or omission of the [Subcontractor]...”. The case involved a construction defect lawsuit filed by a condominium association against MT Builders (MTB), the general contractor, and at least nineteen subcontractors, including Fisher Roofing, Inc. MTB tendered defense of the case to its subcontractors and filed cross-claims for indemnity against the subcontractors. The subcontractors declined to defend MTB. Eventually, MTB settled the association's claims. In turn, MTB then settled its claims against all of the subcontractors except Fisher, the roofing subcontractor. The trial court considered competing motions for summary judgment filed by Fisher and MTB, and ruled in MTB’s favor on the indemnity claims, establishing $240,523 as the portion of the settlement attributable to Fisher. The appeals court reversed and issued three rulings that <strong><em>substantially</em></strong> impact owners, developers, contractors and subcontractors relating to indemnity obligations on construction projects. </p>Jeffrey Steffen
<p>On November 13, 2008, the Arizona Court of Appeals issued its decision in <em>MT Builders, LLC v. Fisher Roofing, Inc.</em>, interpreting a “narrow form” subcontract indemnity provision which reads, in part as follows: “the [Subcontractor] shall indemnify and hold harmless [General Contractor] ... from and against all claims . . . arising out of [Subcontractor’s] work . . . <strong><em>to the extent</em></strong> caused in whole or in part by any negligent act or omission of the [Subcontractor]...”. The case involved a construction defect lawsuit filed by a condominium association against MT Builders (MTB), the general contractor, and at least nineteen subcontractors, including Fisher Roofing, Inc. MTB tendered defense of the case to its subcontractors and filed cross-claims for indemnity against the subcontractors. The subcontractors declined to defend MTB. Eventually, MTB settled the association's claims. In turn, MTB then settled its claims against all of the subcontractors except Fisher, the roofing subcontractor. The trial court considered competing motions for summary judgment filed by Fisher and MTB, and ruled in MTB’s favor on the indemnity claims, establishing $240,523 as the portion of the settlement attributable to Fisher. The appeals court reversed and issued three rulings that <strong><em>substantially</em></strong> impact owners, developers, contractors and subcontractors relating to indemnity obligations on construction projects. </p>
<p><strong>ENFORCEMENT OF NARROW FORM INDEMNITY CLAUSES</strong></p>
<p>First and foremost, the appellate court interpreted the “narrow form” indemnity clause to mean MTB can recover from Fisher only if MTB proves <em>at trial</em> that its losses and expenses were caused, in whole or in part, by Fisher’s negligence, with the recovery limited <strong><em>to the extent</em></strong> of that causation. In short, a narrow form of indemnity requires a trial to determine whether the indemnifying party (Fisher) is responsible at all and, if so, the indemnified party (MTB) will be entitled to recovery for that portion of the damages incurred in connection with the lawsuit against it.</p>
<p><strong>INDEMNITY FOR SETTLEMENT AMOUNTS PAID</strong></p>
<p>Given that most construction defect cases are settled, the second key ruling in <em>MT Builders</em> was that the appeals court also required MTB to demonstrate that the amount it paid to settle the Fisher-based claims was reasonable and prudent. The court listed a matrix of factors to be considered in deciding reasonableness and prudence, including (1) the association's damages, (2) the merits of the association's liability theories, (3) the merits of MTB’s defense theories, (4) MTB’s relative fault, (5) the risks and expenses of continued litigation, (6) any evidence of bad faith, collusion or fraud, (7) the extent of the association's investigation and preparation of the case, and (8) the interests of other parties. Under <em>MT Builders</em>, therefore, a party seeking indemnity for settlement amounts paid must establish at trial that the settlement was prudent and reasonable using a variety of factors.</p>
<p><strong>NO DUTY TO DEFEND</strong></p>
<p>The third and final important indemnity ruling is that Fisher did not have a duty to defend MTB, upon a tender of defense, because the word “defend” was absent from the narrow form indemnity clause at issue. The court found that the “to the extent” language precluded a duty to defend when the duty is not expressly provided because Fisher did not have an obligation to indemnify at all until a determination was made about the extent of Fisher’s fault. The court also suggested that the “to the extent” language in the indemnity may render even an express defense obligation unenforceable because the defense obligation could only arise after liability is established and that would be too late in the proceedings to be a meaningful defense. Practically speaking, that ruling means reimbursement of defense costs from the indemnifying party under narrow form indemnity clauses will not occur until the indemnifying party’s fault has been determined, with that degree of fault applied proportionally for reimbursement of the indemnified party’s attorneys’ fees, legal costs and other expenses.</p>
<p><strong>LESSONS TO BE LEARNED</strong></p>
<p>Contractors, owners and developers negotiating contracts should be aware that under the <em>MT Builders</em> decision, the practical effects of narrow form indemnity clauses, which limit a party’s indemnity obligations “<em><strong>to the extent</strong></em>” of fault caused by the indemnifying party, will be to require a trial determination of fault as a prerequisite to indemnity from the indemnifying party. Contract negotiators concerned about reducing the potential for litigation triggered to enforce an indemnity may wish to consider alternative, broader forms of indemnification consistent with applicable law. Further, before finalizing a settlement with a claimant, contractors, owners and/or developers who intend to seek indemnity under a narrow form indemnity clause with the requisite “to the extent” language must be careful to address and, perhaps, document during the settlement process the various factors under <em>MT Builders</em> relating to the reasonableness of a settlement. Additionally, <em>MT Builders</em> demonstrates the importance of including appropriate “defense” language in indemnity clauses, and the need to consider how an express defense obligation may be enforced if the indemnifying party’s obligations only arise after its liability is established. Finally, note that this decision relates to an indemnity clause that by its terms provided indemnity for “negligence” based claims only. Whether these principles apply to indemnification for damages resulting from the kinds of claims not addressed in the decision, such as contract breaches, remains to be seen. </p>
Arizona Supreme Court Rules on Contract Provisions Capping Damagesurn:uuid:73383D59-1422-1360-CCDF7DC1043711132008-11-06T12:11:00Z2008-11-06T02:11:00Z<p>Professional service contracts often include provisions that limit the service providers’ liability to the amount received under the contract. In a decision earlier this year, the Arizona Court of Appeals ruled that, under the Arizona constitution, the decision whether and how to enforce such provisions must be made by the jury, rather than the judge. 1800 Ocotillo, LLC v. The WLB Group, Inc., No. 1 CA-CV 07-0037. In reaching this conclusion, the Court of Appeals analogized the provision to the defense of “assumption of risk,” which, under the Arizona Constitution, must be submitted to the jury.Fennemore Craig addressed this decision in a litigation update on February 25, 2008. In that update we noted that, “[i]t will be challenging for defendants, seeking to rely upon such provisions, to persuade juries to apply them in situations where the injured party’s damages greatly exceed the limit in the contract.”</p>Christopher L. Callahan
<p>Professional service contracts often include provisions that limit the service providers’ liability to the amount received under the contract. In a decision earlier this year, the Arizona Court of Appeals ruled that, under the Arizona constitution, the decision whether and how to enforce such provisions must be made by the jury, rather than the judge. <em>1800 Ocotillo, LLC v. The WLB Group, Inc.</em>, No. 1 CA-CV 07-0037. In reaching this conclusion, the Court of Appeals analogized the provision to the defense of “assumption of risk,” which, under the Arizona Constitution, must be submitted to the jury.Fennemore Craig addressed this decision in a litigation update on February 25, 2008. In that update we noted that, “[i]t will be challenging for defendants, seeking to rely upon such provisions, to persuade juries to apply them in situations where the injured party’s damages greatly exceed the limit in the contract.”</p>
<p>The Arizona Supreme Court granted review of the Court of Appeals’ decision and reinstated the trial court ruling, holding “that the liability-limitation clause is neither contrary to public policy nor subject to Arizona’s constitutional requirement that the defense of assumption of risk always be submitted to a jury.” The underlying dispute between a developer and a survey company alleged that the survey company was negligent in failing to identify an existing right-of-way resulting in delays and modifications to the development. A provision in the contract between the developer and the survey company limited the developer’s recoverable damages for the survey company’s negligence to the “total fees actually paid” to the survey company. The trial court granted partial summary judgment in favor of the survey company, holding that this provision was enforceable. The court of appeals reversed on the grounds that, under the Arizona Constitution, issues regarding the enforcement of the provision should have been resolved by a jury and that the trial court was wrong in deciding the issue on summary judgment.</p>
<p>The Arizona Supreme Court disagreed with the “assumption of the risk” analogy, stating ‘assumption of risk’ as used in [the Arizona Constitution] . . . refer[s] only to defenses that effectively relieve the defendant of any duty.” The Court concluded the limitation of liability clause was not such a defense and, therefore, the issue of its validity and enforceability did not require determination by the jury. </p>
<p>The Supreme Court also discussed the benefits of such provisions in a manner to suggest it supported their judicial enforcement. The Court noted these provisions “may desirably allow the parties to allocate as between themselves the risks of damages in excess of the agreed-upon cap, which could preserve incentives for one party to take due care while assigning the risk of greater damages to another party that might be better able to mitigate or insure against them.” The Supremem Court did, howvere, recognize potential defenses to the enforceability of these provisions. Specifically, the Court noted that a cap on damages could be challenged by showing that the parties had not negotiated the provision, that the provision was applied in a manner contrary to the parties’ reasonable expectations, that the provision would cap damages at a dollar amount so low as to effectively eliminate the incentive to take precautions, or that the provision resulted from coercive or otherwise improper bargaining.</p>
<p> </p>
Bovis Strikes Back - Nevada Supreme Court Takes Mulligan On Pay-if-Paidurn:uuid:55551FE7-1422-1360-CC70AD8FB1C715E82008-10-31T04:10:00Z2008-11-17T05:11:00Z<p>In June, the Nevada Supreme Court released its opinion in <em>Bovis v. Bullock</em>, 124 Nev. Adv. Op. 39, 185 P.3d 1055 (June 2008). See <a href="http://www.fclaw.com/construction-law/blog/post.cfm/nevada-supreme-court-decides-enforceability-of-contractual-lien-waiver-provisions" target="_blank">this blog post</a> on the case for details of the facts. In the Court's June opinion, it held that pay-if-pay provisions in subcontract agreements violate Nevada public policy. Although the subcontract at issue was entered into before the 2001 amendments to NRS Chapter 624, the Court declared in Footnote 33 that the prompt payment sections included in the 2001 amendments render pay-if-paid provisions unenforceable for contracts entered into after the amendments.</p>
<p>Now, the Supreme Cout has withdrawan its June opinion and replaced it with <a href="http://www.nvsupremecourt.us/documents/advOpinions/124NevAdvOpNo92.pdf" target="_blank"><em>Bovis v. Bullock</em>, 124 Nev. Adv. Op. 92 (Oct. 30, 2008)</a>. </p>Anthony Golden
<p>In June, the Nevada Supreme Court released its opinion in <em>Bovis v. Bullock</em>, 124 Nev. Adv. Op. 39, 185 P.3d 1055 (June 2008). See <a href="http://www.fclaw.com/construction-law/blog/post.cfm/nevada-supreme-court-decides-enforceability-of-contractual-lien-waiver-provisions" target="_blank">this blog post</a> on the case for details of the facts. In the Court's June opinion, it held that pay-if-pay provisions in subcontract agreements violate Nevada public policy. Although the subcontract at issue was entered into before the 2001 amendments to NRS Chapter 624, the Court declared in Footnote 33 that the prompt payment sections included in the 2001 amendments render pay-if-paid provisions unenforceable for contracts entered into after the amendments.</p>
<p>Now, the Supreme Cout has withdrawan its June opinion and replaced it with <a href="http://www.nvsupremecourt.us/documents/advOpinions/124NevAdvOpNo92.pdf" target="_blank"><em>Bovis v. Bullock</em>, 124 Nev. Adv. Op. 92 (Oct. 30, 2008)</a>. The new opinion changes nothing with respect to pay-if-paid provisions entered into before the 2001 amendments. The Court stuck with its previous conclusion "that pay-if-paid provisions are unenforceable because they violate public policy." The notable difference in this new opinion, however, is in Footnote 50. There, the Court states, "Pay-if-paid provisions entered into subsequent to the Legislature's amendments <strong>are enforceable</strong> only in limited circumstances and are subject to the restrictions laid out in these sections. 2001 Nev. Stat., ch. 341, §§ 5-6, at 1615-18." (emphasis added).</p>
<p>The statutes the Court refers to are NRS 624.624 and NRS 624.626. NRS 624.624 governs payment by higher-tiered contractors to lower-tiered subcontractors. If there is a written agreement that includes a schedule of payments, the statute requires payment on the due date or within 10 days of receiveing payment for the work, whichever is earlier. If there is no payment schedule, it reqires payment within 30 days after the lower-tiered subcontractor submits a request for payment or within 10 days of receiving payment for the work, whichever is earlier. NRS 624.626 provides lower-tiered subcontractors with the ability to stop work if they have not received payment as required and they meet certain notice prerequisites.</p>
<p>Where does this leave us? It leaves us with the following unanswered question: what are the "limited circumstances" in which pay-if-paid provisions entered into subsequent to the 2001 amendments are enforceable? The open question is the benefit of this opinion over the withdrawan <em>Bovis</em> opinion. In the former opinion, the Court conclusively said that pay-if-paid provisions entered into after the 2001 amendments were unenforceable. Period. But that issue was not before the Court in the case because the provision in question was entered into before the amendments to the statutes. With this new opinion, the Court allows itself the ability to address the question head on when it is duly raised. It is anyone's guess how the Court will interpret NRS 624.624 and 624.626, but at least the question is open, to be answered on an appropriate set of facts.</p>
Is a Lien Claimant Entitled to Post-Judgment Attorney Fees? urn:uuid:20E6EE2C-1422-1360-CC0ECF643D78E89F2008-10-21T12:10:00Z2008-10-22T08:10:00Z<p>In <em>Carl B. Barney v. Mt. Rose Heating & Air Conditioning</em>, 124 Nev. Adv. Op. 71 (Sept. 18, 2008), the Nevada Supreme Court addressed, among other things: (1) whether NRS 108.237(1), which allows for recovery of attorney’s fees in a mechanic’s lien action, covers all fees incurred to enforce the mechanic’s lien, including those post-judgment attorney fees incidental to the lien’s enforcement through foreclosure; and (2) whether the district court erred in denying a post-judgment motion to enter satisfaction of the judgment because not all of the attorney fees were paid. Carl B. Barney (“<em>Barney</em>”) contracted with Reno Construction, Inc. (“<em>RCI</em>”) to renovate his house. RCI subcontracted with Mt. Rose Heating & Air Conditioning (“<em>Mt. Rose</em>”) to provide equipment and services as part of the renovations. Barney refused to pay for the work, which he determined was defective, and RCI and Mt. Rose filed mechanic’s liens against the property. Both RCI and Mt. Rose obtained judgments and decrees of foreclosure against Barney. Mt. Rose, prior to any foreclosure sale, garnished funds Barney held in a bank, and attempted to execute upon Barney’s personal property. Barney filed and won a motion to exempt his bank account from execution and to quash the garnishment. Mt. Rose sought supplemental attorney fees and costs (“<em>First Mt. Rose Motion</em>”); the court granted their request. Later, Mt. Rose filed a supplemental motion (“<em>Second Mt. Rose Motion</em>”), seeking fees for post-judgment matters, including the judgment’s execution, the garnishment, and the release of Barney’s bank funds. </p>Jeffrey Steffen
<p>In <em>Carl B. Barney v. Mt. Rose Heating & Air Conditioning</em>, 124 Nev. Adv. Op. 71 (Sept. 18, 2008), the Nevada Supreme Court addressed, among other things: (1) whether NRS 108.237(1), which allows for recovery of attorney’s fees in a mechanic’s lien action, covers all fees incurred to enforce the mechanic’s lien, including those post-judgment attorney fees incidental to the lien’s enforcement through foreclosure; and (2) whether the district court erred in denying a post-judgment motion to enter satisfaction of the judgment because not all of the attorney fees were paid. Carl B. Barney (“<em>Barney</em>”) contracted with Reno Construction, Inc. (“RCI”) to renovate his house. RCI subcontracted with Mt. Rose Heating & Air Conditioning (“<em>Mt. Rose</em>”) to provide equipment and services as part of the renovations. Barney refused to pay for the work, which he determined was defective, and RCI and Mt. Rose filed mechanic’s liens against the property. Both RCI and Mt. Rose obtained judgments and decrees of foreclosure against Barney. Mt. Rose, prior to any foreclosure sale, garnished funds Barney held in a bank, and attempted to execute upon Barney’s personal property. Barney filed and won a motion to exempt his bank account from execution and to quash the garnishment. Mt. Rose sought supplemental attorney fees and costs (“<em>First Mt. Rose Motion</em>”); the court granted their request. Later, Mt. Rose filed a supplemental motion (“<em>Second Mt. Rose Motion</em>”), seeking fees for post-judgment matters, including the judgment’s execution, the garnishment, and the release of Barney’s bank funds. </p>
<p>While this <a href="http://www.fclaw.com/construction-law/blog/">supplemental motion</a> was before the court, Barney paid Mt. Rose an amount to satisfy the judgment and the attorney fees and costs awarded in the First Mt. Rose Motion; however, Mt. Rose refused to recognize the judgment as fully satisfied. Barney moved the district court for an order directing the clerk to enter satisfaction of the judgment. Mt. Rose opposed the motion, asserting it was willing to provide a partial satisfaction, but was entitled to additional awards of attorney fees (requested in the Second Mt. Rose Motion), and the court denied the motion. Just over three (3) weeks after denying Barney’s motion, the court granted the Second Mt. Rose Motion for fees and costs. Barney appealed the post-judgment orders, arguing that the court was not authorized to award attorney fees incurred after the original judgment, and, even if authorized, the fees were unreasonable. Barney also argued the district court should have directed the clerk to enter the judgment’s satisfaction. The Court held that NRS 108.237(1) covers not only pre-judgment fees and costs, but also costs and fees that are incidental to the lien’s enforcement. Since the enforcement action ends only when the property is sold and the proceeds are distributed (or otherwise paid) and the lien is discharged or released, costs and fees up to this point are properly awarded (so long as they are incidental to the lien’s enforcement). Additionally, the Court held that since Mt. Rose had a motion for attorney fees pending at the time Barney tendered payment for the judgment, Barney was only entitled to partial satisfaction of judgment, and affirmed the finding of the district court.</p>
Nevada Supreme Court Clarifies its Definition of a "New Residence" for NRS Chapter 40urn:uuid:1B64AAE2-1422-1360-CC835D8431135EF92008-10-20T10:10:00Z2008-10-21T12:10:00Z<p>In <em>ANSE, Inc., d/b/a Nevada State Plastering v. The Eighth Judicial District Court</em>, 124 Nev. Adv. Op. 74 (Sept. 25, 2008), the Nevada Supreme Court clarified whether their definition of a “new residence”, as decided in Westpark Owners’ Ass’n v. District Court (123 Nev. ___, 167 P.3d 421 (2007); <a href="http://www.fclaw.com/construction-law/blog/post.cfm/court-defines-new-residence-and-addresses-buyer-waivers-of-constructional-defect-claims">see blog post from June 27, 2008</a>), precluded a homeowner who is not the home’s first purchaser from seeking remedies available under NRS Chapter 40 for constructional defects. In Westpark, the Court interpreted “new residence” as a product of original construction that has been unoccupied as a dwelling from the completion its construction until its sale. In this case, approximately 700 of the residences at issue in the constructional defect case were occupied as dwellings before the residences’ subsequent owners obtained title to the homes. Relying on Westpark, petitioners sought summary judgment as to their NRS Chapter 40 liability on claims related to those residences.</p>Jeffrey Steffen
<p>In <em>ANSE, Inc., d/b/a Nevada State Plastering v. The Eighth Judicial District Court</em>, 124 Nev. Adv. Op. 74 (Sept. 25, 2008), the Nevada Supreme Court clarified whether their definition of a “new residence”, as decided in Westpark Owners’ Ass’n v. District Court (123 Nev. ___, 167 P.3d 421 (2007); <a href="http://www.fclaw.com/construction-law/blog/post.cfm/court-defines-new-residence-and-addresses-buyer-waivers-of-constructional-defect-claims">see blog post from June 27, 2008</a>), precluded a homeowner who is not the home’s first purchaser from seeking remedies available under NRS Chapter 40 for constructional defects. In Westpark, the Court interpreted “new residence” as a product of original construction that has been unoccupied as a dwelling from the completion its construction until its sale. In this case, approximately 700 of the residences at issue in the constructional defect case were occupied as dwellings before the residences’ subsequent owners obtained title to the homes. Relying on Westpark, petitioners sought summary judgment as to their NRS Chapter 40 liability on claims related to those residences. </p>
<p>The Court found that petitioner’s expansion of “new residence” in Westpark as precluding a homeowner who is not the home’s original purchaser from obtaining remedies available under NRS Chapter 40 violates that chapter’s spirit, leads to unreasonable and absurd results, and ignores Westpark’s unique factual background. While rejecting petitioner’s claim, the Court recognized it needed to better clarify the definition of “new residence”. The Court indicated a “new residence” under NRS 40.615 is one that has remained unoccupied as a dwelling from the completion of its construction to the point of its first sale. Thereafter, subsequent owners of that residence, as claimants, may seek NRS Chapter 40’s residential constructional defect remedies, so long as the action is instituted within the applicable statute of repose.</p>
Contractor's License is Intangible Personal Property that is Subject to a Claim for Conversionurn:uuid:0B4EF2BA-E9AA-6BC0-74F70B36D8B737142008-10-17T07:10:59Z2008-10-17T06:10:00Z<p>In <em>M.C. Multi-Family Dev. v. Crestdale Assoc.</em>, 124 Nev. Adv. Op. No. 77
(Oct. 2, 2008), the Nevada Supreme Court concluded that a contractor's
license is the personal property of the entity or individual named on
the license. Therefore, it is subject to a claim of conversion if
another entity or individual exercises "wrongful dominion" over the
license. The qualifying employee of Walter Homes, Ltd. used Walter
Homes' contractor's license to develop real property under a separate
company, Crestdale Associates, Ltd., without the permission of the
majority interest owners of Walter Homes. During trial, after the
plaintiff's case in chief, the district court entered a directed
verdict against the plaintiff's conversion claim. The district court
found that Crestdale Associates had not "taken" the license.</p>Anthony Golden
<p>In <em>M.C. Multi-Family Dev. v. Crestdale Assoc.</em>, 124 Nev. Adv. Op. No. 77 (Oct. 2, 2008), the Nevada Supreme Court concluded that a contractor's license is the personal property of the entity or individual named on the license. Therefore, it is subject to a claim of conversion if another entity or individual exercises "wrongful dominion" over the license. The qualifying employee of Walter Homes, Ltd. used Walter Homes' contractor's license to develop real property under a separate company, Crestdale Associates, Ltd., without the permission of the majority interest owners of Walter Homes. During trial, after the plaintiff's case in chief, the district court entered a directed verdict against the plaintiff's conversion claim. The district court found that Crestdale Associates had not "taken" the license.<br /><br />On appeal, the Nevada Supreme Court determined first that a contractor's license embodies the intangible rights of the entity or person named on the license, and it is therefore intangible personal property subject to a conversion claim under Nevada law. Second, the Court concluded that a claimant for conversion of a contractor's license need not establish a physical "taking" of the license. "While the unauthorized use of a contractor's license does not involve an actual physical appropriation or 'taking' as the district court concluded, it nonetheless may constitute an act inconsistent with the rights of the titleholder. . . ." Accordingly, the Court reversed the district court's directed verdict and remanded the case for a jury trial on the conversion claim.<br /> <br /><strong>Note to qualified employees:</strong><br />The Court specifically held that a person's status as the qualified employee does not give that person an "ownership or possessor interest in the corporate contractor's license and . . . such license can only be used by the individual or entity to which it is issued."</p>
Court Holds Discretionary Immunity Protects Governmental Entity from Tort Liability in Accepting or Rejecting Bids for Public Works Projectsurn:uuid:0B48E448-0F2A-880A-360331FBFFCAAD3D2008-10-17T07:10:59Z2008-10-17T07:10:00Z<p>The Nevada Supreme Court held recently that a Boulder City engineer's
requirement that a low-bidding general contractor replace a particular
subcontractor before the City would accept the bid was an action
falling under discretionary immunity and precluded liability against
the City for tortious interference of the subcontractor's contract.
City of Boulder City v. Boulder Excavating, Inc., 124 Nev. Adv. Op. 65
(Sept. 11, 2008). Over a period of several years, Boulder Excavating,
Inc. ("BEI"), as a general contractor, secured several accepted bids
with Boulder City for public works projects. In 2000, however, a
dispute between BEI and Boulder City over a road construction project
occurred and was resolved by protracted arbitration proceedings, after
which both parties claimed to have prevailed.</p>Anthony Golden
<p>The Nevada Supreme Court held recently that a Boulder City engineer's requirement that a low-bidding general contractor replace a particular subcontractor before the City would accept the bid was an action falling under discretionary immunity and precluded liability against the City for tortious interference of the subcontractor's contract. <em>City of Boulder City v. Boulder Excavating, Inc.</em>, 124 Nev. Adv. Op. 65 (Sept. 11, 2008). Over a period of several years, Boulder Excavating, Inc. ("BEI"), as a general contractor, secured several accepted bids with Boulder City for public works projects. In 2000, however, a dispute between BEI and Boulder City over a road construction project occurred and was resolved by protracted arbitration proceedings, after which both parties claimed to have prevailed.<br /><br />In late 2000 or early 2001, Boulder City solicited bids for the multimillion dollar Veteran's Memorial Park public works project. McComb Construction, a general contractor, submitted the lowest responsive and responsible bid. McComb's bid, however, included BEI as a subcontractor. Boulder City's engineer, Scott Hansen, requested that McComb seek permission to replace BEI with another subcontractor before accepting McComb's bid. McComb complied with the request, and the City awarded McComb the project.<br /><br />BEI then brought suit against Boulder City and Hansen for, among other things, (1) intentionally interfering with the contractual relationship between McComb and BEI; (2) conspiring to evade the public bidding requirements of NRS Chapter 338; and (3) denying BEI of its rights to perform subcontract work. BEI's claims against Boulder City were based on Hansen's conduct as Boulder City's primary government actor. The district court found that Hansen was immune as a governmental actor under NRS 41.032(2). However, despite Hansen's immunity and that the claims against Boulder City were based on Hansen's actions, the court did not find Boulder City immune.<br /><br />On appeal, the Nevada Supreme Court concluded that the district court erred. If Hansen was protected by NRS 41.032(2)'s discretionary immunity as a governmental actor, the agency for which he acted was also protected. Accordingly, the Supreme Court held that Boulder City was also immune because "Hansen was engaged in discretionary acts as defined by NRS 41.032(2), and because he was acting pursuant to his statutory authority in selecting subcontractors under NRS 338.141."<br /><br /><strong>A potential footnote landmine:</strong><br />In footnote 22, the Supreme Court addresses an argument of BEI that immunity should not be extended to Boulder City on BEI's claim of intentional inference with contract because "governmental actors are not entitled to immunity for illegal intentional acts or acts taken in bad faith." In addressing this argument, the Court concluded that because Boulder City had not accepted McComb's bid at the time of Hansen's actions, there was no contract with which to interfere. "[A] putative subcontractor named in a public works bid has no protected property interest in the public works contract because no cognizable claim to damages can arise before an award is made." In reaching this conclusion, the Court rejected BEI's argument under <em>Clark Pacific v. Krump Constr., Inc., 942</em> F. Supp. 1324 (D. Nev. 1996).<br /><br />In <em>Clark Pacific</em>, the Nevada Federal District Court concluded that a "psuedo contract" exists between the general contractor and a subcontractor <em>after</em> the public entity awards the project to the general but before a formal contract is signed between the general and the sub. The <em>Clark Pacific</em> court did not address BEI's argument on the issue of whether some sort of contractual relationship exists between the general and the sub before the public entity awards the contract to the general. Therefore, the Nevada Supreme Court is correct that <em>Clark Pacific</em> does not apply to BEI because BEI was substituted before Boulder City had awarded the contract to McComb. The Court, however, did not need to go so far as to say that, for a subcontractor, "no cognizable claim to damages can arise before an award is made." The Court's statement forecloses any possible claim for damages by a subcontractor before the public entity awards project. Depending on future cases that come before the Court, this may become one of those footnotes that the Court retreats from and limits to the facts of this case.<br /><br />For a full copy of the case: <a href="http://www.nvsupremecourt.us/documents/advOpinions/124NevAdvOpNo65.pdf">http://www.nvsupremecourt.us/documents/advOpinions/124NevAdvOpNo65.pdf</a>.</p>
Contractor Liability Under Implied Warranties in Residential Constructionurn:uuid:8AC71395-DBA2-D171-2E846A34A348549F2008-08-30T01:08:16Z2008-09-10T07:09:00Z<p>The Arizona Supreme Court recently ruled that homeowners (and homeowner
associations on behalf of homeowners) may sue residential homebuilders
on an implied warranty of workmanship and habitability even if the
homebuilder was not also the vendor of the homes and the homebuilder
had no other direct relationship with the homebuyer. <em>See The Lofts at Fillmore Condominium Assoc. v. Reliance Commercial Construction</em>, No. CV-07-0416-PR (Ariz. filed Aug. 19, 2008) (<a href="http://www.supreme.state.az.us/opin/pdf2008/ACV070416PR.pdf">http://www.supreme.state.az.us/opin/pdf2008/ACV070416PR.pdf</a>).<br /><br /><strong>How does this work in Nevada?<br /></strong>Nevada has not addressed the situation at issue in Arizona's <em>Lofts at Fillmore</em>
case where the homebuilder was not also the vendor or a joint venturer
with the vendor of the homes. The Nevada Supreme Court, however, has
held that where a homebuilder is a joint venturer with the vendor, both
the homebuilder and the vendor are jointly and severally liable to the
homebuyer for breach of the implied warranty of habitability. <em>See Radaker v. Scott</em>, 109 Nev. 653, 855 P.2d 1037 (1993).</p>Anthony Golden
<p>The Arizona Supreme Court recently ruled that homeowners (and homeowner
associations on behalf of homeowners) may sue residential homebuilders
on an implied warranty of workmanship and habitability even if the
homebuilder was not also the vendor of the homes and the homebuilder
had no other direct relationship with the homebuyer. <em>See The Lofts at Fillmore Condominium Assoc. v. Reliance Commercial Construction</em>, No. CV-07-0416-PR (Ariz. filed Aug. 19, 2008) (<a href="http://www.supreme.state.az.us/opin/pdf2008/ACV070416PR.pdf">http://www.supreme.state.az.us/opin/pdf2008/ACV070416PR.pdf</a>).<br /><br /><strong>How does this work in Nevada?<br /></strong>Nevada has not addressed the situation at issue in Arizona's <em>Lofts at Fillmore</em>
case where the homebuilder was not also the vendor or a joint venturer
with the vendor of the homes. The Nevada Supreme Court, however, has
held that where a homebuilder is a joint venturer with the vendor, both
the homebuilder and the vendor are jointly and severally liable to the
homebuyer for breach of the implied warranty of habitability. <em>See Radaker v. Scott</em>, 109 Nev. 653, 855 P.2d 1037 (1993).<br /><br />Here
is what we know under Nevada law: (1) A hombuilder that is also a
vendor is liable to a homebuyer for breach of the implied warranty of
habitability. (2) A homebuilder that joint ventures with the vendor is
liable to a homebuyer for breach of the implied warranty. The Nevada
Supreme Court in <em>Radaker</em> extensively discussed the history of
the implied warranty of habitability as being based in public policy.
The Court agreed with numerous other courts that the implied warranty
was based on sound public policy: "We agree with the virtual consensus
among courts in our sister states that the implied warranty of
habitability reflects a naturally expected and sound public policy." <em>Radaker</em>, 109 Nev. at 661, 855 P.2d at 1042. The Court then adopted the implied warranty for Nevada. <em>Id</em>.<br /><br />By basing the implied warranty of habitability on public policy rather than on contract, the <em>Radaker</em>
decision provides a stepping stone for the Nevada Supreme Court to go
down the path of Arizona and extend the implied warranty when there is
no contractual privity between the homebuilder and the homebuyer. The
Arizona court in <em>Lofts at Fillmore</em> also based its decision to extend the implied warrant on public policy grounds. "We stressed in <em>Richards</em>
that, given the policies behind the implied warranty – to protect
innocent buyers and hold builders responsible for their work – any
reasoning which would arbitrarily interpose a first buyer as an
obstruction to someone equally deserving of recovery is
incomprehensible." <em>Lofts at Fillmore</em> at 9-10 (internal
quotations and citations omitted). It is not unthinkable then for
Nevada to go one more step like Arizona has and hold that a homebuilder
can be liable to a homebuyer for breach of the implied warranty even if
the homebuilder is merely a contractor of the vendor and has no direct
relationship with the homebuyer and gains no direct benefit from the
sale of the home. We'll have to wait and see when such a case presents
itself to the Nevada Supreme Court.<br /><br />Regardless of how loosely
Nevada may in the future apply the implied warranty of habitability,
any claims based on the implied warranty by a homebuyer would almost
certainly be subject to the requirements of Nevada's construction
defect statutes (NRS 40.600 - 40.695). Therefore, at a minimum, a
homebuilder would have to be given notice of the defect and an
opportunity to cure it before an action can be commenced by a
homebuyer.
</p>
Contractors Must use E-Verify to Verify Workers Employment Eligibility for all Future Federal Contractsurn:uuid:8AC54D02-FF0C-8A68-1CF660C8ED09D3262008-07-09T01:07:21Z2008-09-10T07:09:00Z<p>On June 6, 2008, President Bush issued an <a href="http://www.whitehouse.gov/news/releases/2008/06/20080609-2.html">Executive Order</a>
amending Executive Order 12989, which directs all Federal departments
and agencies to require contractors, as a condition of each future
federal contract, to agree to use an electronic employment eligibility
verification system (designated by the Secretary of Homeland Security)
to verify the employment eligibility of: (1) all persons hired during
the contract term by the contractor to perform employment duties within
the United States; and (2) all persons assigned by the contractor to
perform work within the United States on the federal contract.</p>Anthony Golden
<p>On June 6, 2008, President Bush issued an <a href="http://www.whitehouse.gov/news/releases/2008/06/20080609-2.html">Executive Order</a>
amending Executive Order 12989, which directs all Federal departments
and agencies to require contractors, as a condition of each future
federal contract, to agree to use an electronic employment eligibility
verification system (designated by the Secretary of Homeland Security)
to verify the employment eligibility of: (1) all persons hired during
the contract term by the contractor to perform employment duties within
the United States; and (2) all persons assigned by the contractor to
perform work within the United States on the federal contract.<br /><br />The
Department of Homeland Security recently designated E-Verify as the
electronic employment eligibility verification system to be used
pursuant to Executive Order 12989.<br /><br />For more detailed information see <a href="http://www.fclaw.com/newsletter/materials/Immigration_Update_6-18-08.pdf">here</a>.<br /><br />E-Verify can be accessed through the <a href="http://www.dhs.gov/xprevprot/programs/gc_1185221678150.shtm">Department of Homeland Security's website</a>.
</p>
Nevada Supreme Court Decides Enforceability of Contractual Lien Waiver Provisionsurn:uuid:8AC0C292-D7E8-BABB-24C30CDA1C352E6B2008-06-28T01:06:27Z2008-09-10T07:09:00Z<p>The Nevada Supreme Court recently addressed two issues of concern to
contractors and owners: (1) the enforceability of lien waiver
provisions, and (2) the enforceability of pay-if-paid provisions. <span style="font-style: italic;">Lehrer McGovern Bovis, Inc. v. Bullock Insulation, Inc.</span>,
124 Nev. Adv. Op. 39 (June 2008), is the latest saga from the Venetian
mechanics' lien lawsuits. The case involved the owner and general
contractor attempting to foil a subcontractor's lien foreclosure and
breach of contract claims by asserting a lien waiver provision and a
pay-if-paid provision in the subcontract agreement<span style="font-style: italic;">. </span>The
Court declared that Nevada's public policy "favor[s] contractors'
rights to secured payment for labor, materials, and equipment
furnished." Based on this policy, the Court struck down both the lien
waiver provision and the pay-if-paid provision. The subcontract
agreement at issue predated the legislative amendments to the
mechanics' lien statutes, NRS Chapter 108, requiring specific forms for
lien waivers and predated the amendments to NRS Chapter 624, which
created Nevada's prompt payment statutes. Although not at issue, the
Court thought it necessary to state, without explanation or analysis in
what will become known as the infamous Footnote 33, that the amendments
to Chapter 624 creating the prompt pay statutes, "make pay-if-paid
provisions entered into subsequent to the Legislature's amendments
unenforceable."<span style="font-size: 100%;"><br /></span></p>Anthony Golden
<p>The Nevada Supreme Court recently addressed two issues of concern to
contractors and owners: (1) the enforceability of lien waiver
provisions, and (2) the enforceability of pay-if-paid provisions. <span style="font-style: italic;">Lehrer McGovern Bovis, Inc. v. Bullock Insulation, Inc.</span>,
124 Nev. Adv. Op. 39 (June 2008), is the latest saga from the Venetian
mechanics' lien lawsuits. The case involved the owner and general
contractor attempting to foil a subcontractor's lien foreclosure and
breach of contract claims by asserting a lien waiver provision and a
pay-if-paid provision in the subcontract agreement<span style="font-style: italic;">. </span>The
Court declared that Nevada's public policy "favor[s] contractors'
rights to secured payment for labor, materials, and equipment
furnished." Based on this policy, the Court struck down both the lien
waiver provision and the pay-if-paid provision. The subcontract
agreement at issue predated the legislative amendments to the
mechanics' lien statutes, NRS Chapter 108, requiring specific forms for
lien waivers and predated the amendments to NRS Chapter 624, which
created Nevada's prompt payment statutes. Although not at issue, the
Court thought it necessary to state, without explanation or analysis in
what will become known as the infamous Footnote 33, that the amendments
to Chapter 624 creating the prompt pay statutes, "make pay-if-paid
provisions entered into subsequent to the Legislature's amendments
unenforceable."<span style="font-size: 100%;"><br /><span style="font-size: 100%;"><br /></span></span><span style="font-weight: bold; font-size: 100%;">Mechanics' Lien Waivers</span><br />The
subcontract agreement between subcontractor Bullock Insulation and
general contractor Bovis incorporated a provision from the general
conditions in which Bullock Insulation promised "'not [to] suffer or
permit any lien or other encumbrance to be filed' against the project."
The Court noted that the "lien waiver provision applies regardless of
whether Bullock Insulation received any payment" and therefore
concluded that "such provision violates public policy, as it fails to
secure payment for Bullock Insulation."<br /><br />The Court assured that
not every lien waiver provision violates public policy and that the
enforceability of a lien waiver clause must be decided on a
case-by-case basis. Limiting the enforceability of lien waiver
provisions to the facts of each case seems like a fair result, but the
Court gave no guidance as to what types of lien waiver provisions would
be enforceable without payment in full. The public policy proclamation
coupled with NRS 108.2453(1), which prohibits the waiver of mechanics'
lien rights unless the appropriate forms specified in Chapter 108 are
completed and payment made, suggest that without payment in full,
mechanics' lien rights can not be waived.<br /><br /><span style="font-weight: bold; font-size: 100%;">Pay-If-Paid Provisions</span><br />More
disturbing than the Court's treatment of the lien waiver provision is
its decision on the pay-if-paid provision. The subcontract agreement
contained a pay-if-paid provision whereby Bullock Insulation's right to
payment for its work was contingent upon payment by the owner to Bovis.
The Court held the provision unenforceable because "a pay-if-paid
provision limits a subcontractor's ability to be paid for work already
performed" and therefore "such a provision impairs the subcontractor's
statutory right to place a mechanic's lien on the construction
project." Rather than limit the holding to a case-by-case analysis,
however, the Court concluded that all pay-if-paid provisions that were
entered into before the amendments to NRS Chapter 624 are unenforceable.<br /><br />What's more, in Footnote 33, the Court proclaimed,</p>
<blockquote>We
note that in 2001, the Legislature amended NRS Chapter 624 to include
prompt payment provisions contained in NRS 624.624 through 624.626,
which <span style="font-style: italic;">make pay-if-paid provisions entered into subsequent to the Legislature's amendments unenforceable</span>. (emphasis added).<br /></blockquote>
<p>The
Court acknowledged that the amendment to Chapter 624 "does not affect
our analysis here because it is not retroactive." Yet, the Court rang
the bell anyway.<br /><br />A major problem with Footnote 33 is that the
prompt payment statutes in Chapter 624 do not render pay-if-paid
clauses unenforceable. In fact, NRS 624.626(1)(b) recognizes that
pay-if-paid or pay-when-paid provisions regularly exist in subcontract
agreements and grants the subcontractor the remedy of stopping work
when a higher-tiered contractor does not timely pay a lower-tiered
contractor even if the higher-tiered contractor has not been paid by
the owner. Additionally, pay-if-paid provisions do not necessarily
eliminate a subcontractor's mechanic's lien rights. Even with a
pay-if-paid provision in a subcontract agreement, the subcontractor
remains able perfect and foreclose on its mechanic's lien against the
owner. Despite these remedies, Footnote 33 effectively makes the
general contractor a lender of the owner by requiring general
contractors to pay subcontractors when the general has not received
payment from the owner. This is true even if the subcontractor has
assumed the risk of nonpayment by agreeing to a pay-if-paid provision.<br /><br /><span style="font-weight: bold; font-size: 100%;">Where To Go From Here</span><br />Undoubtedly, the <span style="font-style: italic;">Bovis</span>
decision will draw a lot of criticism. A motion for rehearing would not
be surprising. The decision makes it more important than ever for
general contractors to verify the financial viability of owners to
complete a project. So far, the decision appears favorable to
subcontractors that are subject to now-unenforceable lien waiver and
pay-if-paid provisions. Owners should expect post-<span style="font-style: italic;">Bovis</span>
contracts to attempt to allocate more heavily to the owner the general
contractor's risk of liability to subcontractors for owner nonpayment.
But even a reallocation of risk cannot protect a general contractor
from an insolvent owner.
</p>
Does NRS Chapter 40 Apply to Completed Blueprints for an Unfinished Residence?urn:uuid:8ABAEAC4-DC9B-F72D-94898023585248012008-06-27T01:06:25Z2008-09-10T07:09:00Z<p>The quick answer is "No". In Pankopf v. Peterson, ___ Nev. ___, 175
P.3d 910 (2008), the Pankopfs entered into a contract with Peterson for
residential design and drawing services for a personal residence.
Peterson provided blueprints for a personal residence, and excavation
for the residence’s construction began. The plans failed to identify
the types of trees that would be planted on the site as required by the
Pankopf’s homeowner’s association, and the excavation process was
halted. According to the Pankopfs, a number of deficiencies in
Peterson's work ultimately prevented them from building their
residence. The Pankopfs brought suit against Peterson, alleging that
Peterson's plans contained numerous design defects, mistakes,
omissions, and inaccuracies that prevented them from constructing the
residence. Peterson subsequently filed a motion to dismiss under NRCP
12(b)(5), arguing that the Pankopfs failed to comply with certain
requirements set forth in NRS Chapter 40 that applied in constructional
defect cases. The Pankopfs argued that they did not make a claim for
relief based on any constructional defect within the scope of NRS
Chapter 40.</p>Jeffrey Steffen
<p>The quick answer is "No". In Pankopf v. Peterson, ___ Nev. ___, 175
P.3d 910 (2008), the Pankopfs entered into a contract with Peterson for
residential design and drawing services for a personal residence.
Peterson provided blueprints for a personal residence, and excavation
for the residence’s construction began. The plans failed to identify
the types of trees that would be planted on the site as required by the
Pankopf’s homeowner’s association, and the excavation process was
halted. According to the Pankopfs, a number of deficiencies in
Peterson's work ultimately prevented them from building their
residence. The Pankopfs brought suit against Peterson, alleging that
Peterson's plans contained numerous design defects, mistakes,
omissions, and inaccuracies that prevented them from constructing the
residence. Peterson subsequently filed a motion to dismiss under NRCP
12(b)(5), arguing that the Pankopfs failed to comply with certain
requirements set forth in NRS Chapter 40 that applied in constructional
defect cases. The Pankopfs argued that they did not make a claim for
relief based on any constructional defect within the scope of NRS
Chapter 40. </p>
<p>The district court granted Peterson's motion, concluding
that because NRS 40.615 defines a constructional defect as a “defect in
the design ... of an alteration of or addition to an existing
residence, or of an appurtenance” and NRS 40.605 defines an
appurtenance as including “the parcel of real property,” the Pankopf’s
claims fell within NRS Chapter 40's purview. The Court, on appeal,
stated that because no residence existed, the parcel of real property
cannot constitute an appurtenance within the meaning of NRS 40.605. In
addition, the Pankopfs primarily complained of mistakes in Peterson's
plans for their house, not in the design of any appurtenance.
Therefore, the Court concluded that the Pankopf’s claims did not fall
under NRS Chapter 40 based on the plain language of the definitions set
forth in NRS 40.615 and NRS 40.605(1). The Court also addressed the
meaning of the term “new residence” as defined by NRS Chapter 40,
citing their recent decision in Westpark Owners' Ass'n v. District
Court (see below). Specifically, the Court held that “a residence is
‘new’ when it is a product of original construction that has been
unoccupied as a dwelling from the completion of its construction until
the point of sale.” Since the Pankopf’s residence has not been
completed, it cannot constitute a “new residence” for the purposes of
NRS Chapter 40. As such, NRS Chapter 40 does not apply to completed
blueprints for unfinished residences.</p>
Court Defines New Residence and Addresses Buyer Waivers of Constructional Defect Claimsurn:uuid:8AB929BF-FF9F-04EC-333914706FAFE1AF2008-06-27T01:06:59Z2008-09-10T07:09:00Z<p>In <em>Westpark Owners’ Association v. Eighth Judicial District Court</em>,
___ Nev. ___, 167 P.3d 421 (2007), the Court addressed three (3) issues
concerning NRS Chapter 40 (constructional defects): i) the definition
of “residence”; ii) the definition of “new”, in the context of a
residence; and iii) the effect of a general waiver of constructional
defects in a sales contract. Westpark Associates, LLC (“<em>Westpark</em>”)
purchased a partially completed condominium project out of bankruptcy,
and completed an additional 108 units, but due to market conditions
decided to lease the 108 units as apartments, and did so from 1997
through 2003. Westpark started selling the units to the general public,
and each contract required the buyer to waive “any” possible
construction defect claims. The converted condo owners began
experiencing problems with their units, and the Westpark Owners’
Association (the “<em>Association</em>”) served Westpark with a formal
Chapter 40 notice. </p>Jeffrey Steffen
<p>In <em>Westpark Owners’ Association v. Eighth Judicial District Court</em>,
___ Nev. ___, 167 P.3d 421 (2007), the Court addressed three (3) issues
concerning NRS Chapter 40 (constructional defects): i) the definition
of “residence”; ii) the definition of “new”, in the context of a
residence; and iii) the effect of a general waiver of constructional
defects in a sales contract. Westpark Associates, LLC (“<em>Westpark</em>”)
purchased a partially completed condominium project out of bankruptcy,
and completed an additional 108 units, but due to market conditions
decided to lease the 108 units as apartments, and did so from 1997
through 2003. Westpark started selling the units to the general public,
and each contract required the buyer to waive “any” possible
construction defect claims. The converted condo owners began
experiencing problems with their units, and the Westpark Owners’
Association (the “<em>Association</em>”) served Westpark with a formal
Chapter 40 notice. </p>
<p>The district court entered partial summary judgment
in favor of Westpark, declaring generally that Westpark had “no
liability” in connection with the development or sale, relying on
several conclusions of law which were revisited by the Nevada Supreme
Court. First, contrary to the district court’s reasoning, the Court
found that the mere fact the units were originally built as apartments
does not prevent them from meeting the definition of a residence. The
Court found the event conferring “residence” status is the transfer of
title to a home purchaser. Second, the Court interpreted “new” as a
product of original construction that has been unoccupied as a dwelling
from the completion its construction until its sale. Although the units
in this matter did not meet the definition of “new”, the Court found
that if Westpark altered or repaired the units before their sale, they
would fall under NRS 40.615. Finally, while NRS 40.640(5) allows a
contractor and homebuyer to stipulate to a waiver of any potential
claims under NRS Chapter 40, the “waived” constructional defect must be
disclosed to the buyer in clear language before the purchase of the
residence. Here, the waivers did not disclose any constructional
defects; they stated only that certain defects “may” exist and listed a
number of potential defects. This general disclaimer language was not
sufficient to waive any claims pursuant to NRS Chapter 40.</p>
Court Creates Reasonable Threshold Test For Constructional Defect Pre-Litigation Noticesurn:uuid:8A923902-A421-1FFE-EC7ADCA12C743BC02008-06-27T12:06:32Z2008-09-03T01:09:00ZJeffrey Steffen
<p>In D.R. Horton v. Eighth Judicial District Court, ___ Nev. ___, 168 P.3d 731 (2007), D.R. Horton, Inc. (“<em>D.R. Horton</em>”) constructed 414 residences in 138 buildings in the First Light at Boulder Ranch Community in Henderson, Nevada (“<em>First Light</em>”).
Believing that numerous constructional defects may exist in each
residence, First Light hired experts to assist it in preparing an NRS
40.645 pre-litigation notice of constructional defects. The notice was
formulated after using visual and invasive testing in a small
representative sampling of homes in the community. First Light did not
provide D.R. Horton with the addresses or the expert report of the
homes that were tested. Using the information they found, the First
Light experts simply extrapolated the percentage of homes in which they
believed each defect existed throughout the community. D.R. Horton
moved the district court for a declaratory judgment, stating that First
Light’s NRS 40.645 notice was unreasonable and thus statutorily
insufficient. The district court denied the motion, and D.R. Horton
filed a writ petition challenging the district court’s order. To
address the problem of what satisfies the “reasonable detail”
requirement of NRS 40.645, the Court formulated the “reasonable
threshold” test to be used when pre-litigation notices contain
extrapolated data. The scope of the extrapolated notice must be narrow.
</p>
<p>First, the homeowner’s expert must test and verify the existence of an
alleged defect in at least one of the homes in each subset of homes
included within the scope of the extrapolated notice. Additionally, the
claimants must provide the address of each home tested and clearly
identify the subset of homes to which the pre-litigation notice
applies. In order to provide valid pre-litigation notice, claimants
must narrow the scope of their extrapolated notice. They should
investigate and identify a subset of homes within the community that
has the purported defect. If they genuinely believe that every home in
the community may have the alleged defect, then the claimants should
test and verify the defect in at least one home from each subset of
homes in the community and extrapolate the percentage of homes within
each subset that they believe are likely to contain the defect. The
court emphasized that the legislature intended NRS 40.645 to provide
Nevada contractors an opportunity to inspect and repair defects in the
homes they construct. To that end, a pre-litigation notice must contain
reasonable detail so that a contractor, who makes the business
decision, can decide whether to inspect and repair. The Court also
concluded that a claimant cannot utilize the phrase “to the extent
known” in NRS 40.645(2)(c) to justify withholding pertinent information
from a pre-litigation notice, and that NRS 40.645(4)(c) requires a
claimant to disclose the expert opinions and reports in its possession
that were used to prepare its pre-litigation notice.</p>