Construction Law Blogtag:www.fclaw.com,2010:/blogs/construction-law/Setting the Standard for Construction Law in the SouthwestMango 1.4Nevada – Commercial design professionals protected from professional negligence claims by economic loss doctrineurn:uuid:C3AB36D5-A0A5-A14F-8940CD57B3DAFF502009-09-04T05:09:40Z2009-09-16T09:09:00Z<p>The Nevada Supreme Court held in <em style="mso-bidi-font-style: normal;">Terracon Consultants Western, Inc. v.
Mandalay Resort Group</em>, 206 P.3d 81 (2009) that, “in a commercial property
construction defect action in which the plaintiffs seek to recover purely
economic losses through negligence-based claims, the economic loss doctrine
applies to bar such claims against design professionals who have provided
professional services in the commercial property development or improvement
process.”<span style="mso-spacerun: yes;">
</span>This holding arises out of a question certified under NRAP 5 from the
United States District Court for the District of Nevada.</p>Anthony Golden
<p>Terracon Consultants Western, Inc. v.
Mandalay Resort Group, 206 P.3d 81 (2009) that, “in a commercial property
construction defect action in which the plaintiffs seek to recover purely
economic losses through negligence-based claims, the economic loss doctrine
applies to bar such claims against design professionals who have provided
professional services in the commercial property development or improvement
process.”<span style="mso-spacerun: yes;">
</span>This holding arises out of a question certified under NRAP 5 from the
United States District Court for the District of Nevada.
</p>
<p class="MsoNormal" style="margin: 0in 0in 0pt;"> </p>
<p class="MsoNormal" style="margin: 0in 0in 0pt;"><em style="mso-bidi-font-style: normal;">The underlying case pending in Federal
District Court</em></p>
<p class="MsoNormal" style="margin: 0in 0in 0pt;"> </p>
<p class="MsoNormal" style="margin: 0in 0in 0pt;">To complete the Mandalay Resort and Casino,
Mandalay hired Terracon Consultants Western, Inc. and a related entity to
provide geotechnical engineering advice about subsurface soil conditions and to
recommend a foundation design.<span style="mso-spacerun: yes;"> </span>It also hired Lochsa, LLC and Klai-Juba
Architects, Ltd. to provide engineering and architectural services to design the
resort’s structure.<span style="mso-spacerun: yes;"> </span>Mandalay had a written contract with
Terracon and oral agreements with Lochsa and Klai-Juba.<span style="mso-spacerun: yes;"> </span>None of these
design professional played a role in the resort’s physical construction.</p>
<p class="MsoNormal" style="margin: 0in 0in 0pt;"> </p>
<p class="MsoNormal" style="margin: 0in 0in 0pt;">Mandalay alleged that Terracon’s soil settling
analysis was wrong and that the amount of settling which actually occurred
exceeded Terracon’s projections.<span style="mso-spacerun: yes;"> </span>Clark County required Mandalay to repair
and reinforce the foundation before it could complete construction.<span style="mso-spacerun: yes;"> </span>Mandalay sued
Terracon for damages, alleging that the deficient engineering advice cause the
foundation problems and that Terracon was liable for breach of contract, breach
of the covenant of good faith and fair dealing, and professional
negligence.<span style="mso-spacerun: yes;">
</span>Terracon filed a third-party complaint against Lochsa and Klai-Juba for
negligence, contribution, and equitable indemnity.</p>
<p class="MsoNormal" style="margin: 0in 0in 0pt;"> </p>
<p class="MsoNormal" style="margin: 0in 0in 0pt;">Terracon moved for partial summary judgment
arguing that the economic loss doctrine barred Mandalay’s professional
negligence claim.<span style="mso-spacerun: yes;"> </span>Lochsa and Klai-Juba also moved to
dismiss Terracon’s negligence claims against them on the same basis.<span style="mso-spacerun: yes;"> </span>The U.S.
district court denied the motions without prejudice and certified the economic
loss question to the Nevada Supreme Court.</p>
<p class="MsoNormal" style="margin: 0in 0in 0pt;"><em style="mso-bidi-font-style: normal;">The question addressed by the Nevada
Supreme Court</em></p>
<p class="MsoNormal" style="margin: 0in 0in 0pt;">The Nevada Supreme Court answered the following
question:<span style="mso-spacerun: yes;">
</span>“Does the economic loss doctrine apply to preclude negligence-based
claims against design professionals, such as engineers and architects, who
provide services in the commercial property development or improvement process,
when the plaintiffs seek to recover purely economic losses?”<span style="mso-spacerun: yes;"> </span>The Court
answered, “Yes.”</p>
<p class="MsoNormal" style="margin: 0in 0in 0pt;"> </p>
<p class="MsoNormal" style="margin: 0in 0in 0pt;"><em style="mso-bidi-font-style: normal;"></em></p>
<p class="MsoNormal" style="margin: 0in 0in 0pt;"><em style="mso-bidi-font-style: normal;">Generally, a plaintiff may not recover
on a negligence claim for “purely economic losses”</em></p>
<p class="MsoNormal" style="margin: 0in 0in 0pt;"> </p>
<p class="MsoNormal" style="margin: 0in 0in 0pt;">The Court delved into the history of the
economic loss doctrine.<span style="mso-spacerun: yes;"> </span>In short, the doctrine marks the boundary
between contract law and tort law, and it ultimately “bars unintentional tort
actions when the plaintiff seeks to recover ‘purely economic losses.’”<span style="mso-spacerun: yes;"> </span><em style="mso-bidi-font-style: normal;">See</em> <em style="mso-bidi-font-style: normal;">Calloway v. City of Reno</em>, 116 Nev.
250, 256, 993 P.2d 1259, 1263 (2000), <em style="mso-bidi-font-style: normal;">overruled on other grounds by</em> <em style="mso-bidi-font-style: normal;">Olson v. Richard</em>, 120 Nev. 240,
241-44, 89 P.3d 31, 31-33 (2004); <em style="mso-bidi-font-style: normal;">Local Joint Exec. Bd. v. Stern</em>, 98
Nev. 409, 411, 651 P.2d 637, 638 (1982).<span style="mso-spacerun: yes;"> </span>The Court reiterated that “unless there
is personal injury or property damage, a plaintiff may not recover in negligence
for economic losses.”<span style="mso-spacerun: yes;"> </span>In general, purely economic losses are
those that result from loses related to the parties’ agreement and not from
personal injury or property damage.</p>
<p class="MsoNormal" style="margin: 0in 0in 0pt;"> </p>
<p class="MsoNormal" style="margin: 0in 0in 0pt;">The policies behind application of the economic
loss doctrine are to ensure that useful economic activity is not deterred by
fear of unlimited liability beyond contract-based recovery.<span style="mso-spacerun: yes;"> </span>It also reduces
the cost of tort actions by providing potential tort victims with a
less-expensive alternative such as insurance.</p>
<p class="MsoNormal" style="margin: 0in 0in 0pt;"> </p>
<p class="MsoNormal" style="margin: 0in 0in 0pt;"><em style="mso-bidi-font-style: normal;">Some exceptions</em></p>
<p class="MsoNormal" style="margin: 0in 0in 0pt;"> </p>
<p class="MsoNormal" style="margin: 0in 0in 0pt;">The Court noted that countervailing policy
considerations have led to exceptions to the bar created by the economic loss
doctrine.<span style="mso-spacerun: yes;">
</span>For example, negligent misrepresentation and professional negligence
actions against attorneys, accountants, real estate professionals, and insurance
brokers still are viable claims.</p>
<p class="MsoNormal" style="margin: 0in 0in 0pt;"> </p>
<p class="MsoNormal" style="margin: 0in 0in 0pt;">For negligent misrepresentation claims, it is
necessary to create sufficient financial pressure to avoid such negligence,
which isn’t created by simply allowing a breach of contract claim.<span style="mso-spacerun: yes;"> </span>Additionally,
for claims against attorneys, accountants, etc., those professionals tend to owe
duties, such as fiduciary duties, whether statutory based or common-law based,
that extend beyond their contracts with their principals.<span style="mso-spacerun: yes;"> </span>Accordingly,
there is an incentive to impose on those professionals additional liability
beyond contract claims when they breach their professional obligations.</p>
<p class="MsoNormal" style="margin: 0in 0in 0pt;"> </p>
<p class="MsoNormal" style="margin: 0in 0in 0pt;">Additionally, the Court was careful to
acknowledge the continued rule from <em style="mso-bidi-font-style: normal;">Olson</em> that allows residential
property owners to assert negligence claims in construction defect actions
brought under NRS Chapter 40, even when purely economic losses are at stake.</p>
<p class="MsoNormal" style="margin: 0in 0in 0pt;"> </p>
<p class="MsoNormal" style="margin: 0in 0in 0pt;"><em style="mso-bidi-font-style: normal;"></em></p>
<p class="MsoNormal" style="margin: 0in 0in 0pt;"><em style="mso-bidi-font-style: normal;">The economic loss doctrine bars
Mandalay’s negligence claim against Terracon</em></p>
<p class="MsoNormal" style="margin: 0in 0in 0pt;"> </p>
<p class="MsoNormal" style="margin: 0in 0in 0pt;">None of the exceptions applied to Terracon,
Lochsa, or Klai-Juba.<span style="mso-spacerun: yes;"> </span>The Court concluded that the duties of
such design professionals are governed by their contracts and any breach of duty
results in only a breach of the contract.<span style="mso-spacerun: yes;"> </span>If Mandalay’s allegations are true, it
suffered purely economic loss as a result of Terracon’s breach of its duties
arising under the contract between it and Mandalay.<span style="mso-spacerun: yes;"> </span>Therefore, the
Court concluded that the economic loss doctrine bars Mandalay’s negligence-based
claims against Terracon. It is also important to note that the economic loss
doctrine also continues to bar recovery on negligence claims for purely economic
losses against contractors and subcontractors in non-Chapter 40 cases.</p>
<p class="MsoNormal" style="margin: 0in 0in 0pt;"> </p>
<p> </p>
Colorado Construction Payment Reform Act of 2009urn:uuid:C3C19439-BADC-B3C3-A4A07CFD900C2A632009-02-25T12:02:02Z2009-09-16T09:09:00Z<p>In an attempt to shorten the time owners have to pay contractors and
subcontractors, the Colorado Legislature introduced <a href="http://www.leg.state.co.us/Clics/CLICS2009A/csl.nsf/fsbillcont3/1C0E1A154FB3D86787257539006772E8?Open&file=095_01.pdf">Colorado
Senate Bill 09-095</a> (the “Construction Payment Reform Act of 2009” (“Act”)).
While the Act is designed to protect contractors and subcontractors, it will
require that everyone in the construction and development industry – including
lenders and owners – adapt.
<p><strong>I. THE ACT</strong></p>
<p style="padding-left: 30px;"><em>A. Who and
what will be impacted?</em><br />As currently drafted, the Act applies to all
private construction contracts worth more than $100,000, except contracts for
the construction of “single-family or multi-family dwellings with no more than
two units.” It also exempts construction contracts that take less than one month
to complete, single payment and unit-price contracts, and contracts payable in
installments or upon completion.</p>
<p style="padding-left: 30px;"><em>B. How the Act
works?</em><br />The Act requires that all contractors and subcontractors be paid
within thirty days after the end of each “billing cycle”, which is a cycle
agreed upon by the contractor and owner under the general contract.
Surprisingly, however, the term “billing cycle” is not currently defined by the
Act. Instead, the Act provides flexibility for the general contractor and owner
to negotiate appropriate billing cycles on a project by project basis. </p>
<p style="padding-left: 30px;">Payment terms that
conflict with the Act are “unenforceable and void.” </p>
</p>FC Admin
<p>In an attempt to shorten the time owners have to pay contractors and
subcontractors, the Colorado Legislature introduced <a href="http://www.leg.state.co.us/Clics/CLICS2009A/csl.nsf/fsbillcont3/1C0E1A154FB3D86787257539006772E8?Open&file=095_01.pdf">Colorado
Senate Bill 09-095</a> (the “Construction Payment Reform Act of 2009” (“Act”)).
While the Act is designed to protect contractors and subcontractors, it will
require that everyone in the construction and development industry – including
lenders and owners – adapt.
<p><strong>I. THE ACT</strong></p>
<p style="padding-left: 30px;"><em>A. Who and
what will be impacted?</em><br />As currently drafted, the Act applies to all
private construction contracts worth more than $100,000, except contracts for
the construction of “single-family or multi-family dwellings with no more than
two units.” It also exempts construction contracts that take less than one
month to complete, single payment and unit-price contracts, and contracts
payable in installments or upon completion.</p>
<p style="padding-left: 30px;"><em>B. How the
Act works?</em><br />The Act requires that all contractors and subcontractors be
paid within thirty days after the end of each “billing cycle”, which is a cycle
agreed upon by the contractor and owner under the general contract.
Surprisingly, however, the term “billing cycle” is not currently defined by the
Act. Instead, the Act provides flexibility for the general contractor and owner
to negotiate appropriate billing cycles on a project by project basis. </p>
<p style="padding-left: 30px;">Payment terms that
conflict with the Act are “unenforceable and void.” </p>
<p style="padding-left: 60px;">1. Contracts
that involve the use of a subcontractor. <br />Regardless of the length of the
billing cycle agreed upon by the general contractor and owner, the subcontractor
is required to submit to the contractor a progress payment invoice
(“Subcontractor Invoice”), on a monthly basis, for work and materials actually
provided during the month to the general contractor. The contractor must
approve all or a portion of the Subcontractor Invoice within seven days. By
approving all or a portion of the progress payment, the contractor does not
waive claims for work not in conformance with the agreement, breach of
agreement, and wrongful acts or omissions. </p>
<p style="padding-left: 60px;">The general
contractor will submit progress payment invoice (“GC Invoice”) to the owner at
the end of each billing cycle as defined in the general contract. The general
contractor must include within the GC invoice, the amounts shown in the
Subcontractor Invoices, less amounts disapproved by the general contractor
within the 7 day window for objection as described above. Unless otherwise
agreed to in the general contract, the owner must pay the contractor within
twenty-five days after receiving the GC Invoice. The contractor is then
required to pay the subcontractors within five days. </p>
<p style="padding-left: 60px;">2. Contracts
that do not involve the use of a subcontractor. <br />At the end of each billing
cycle, the general contractor must submit to the owner the GC Invoice for all
work and materials actually provided. Unless otherwise agreed to in the general
contract, the owner must pay the contractor within thirty days after receiving
the GC Invoice. By approving all or a portion of the progress payment, the
owner does not waive claims for work not in conformance with the agreement,
breach of agreement, and wrongful acts or omissions. </p>
<p style="padding-left: 30px;"><em>C. What
else does the Act do?</em> <br />The Act imposes stiff financial penalties for
failure to timely pay contractors and subcontractors. For instance, if the
owner or contractor fails to promptly pay, it must also pay 12% interest per
annum (or as set forth in the agreement) on the unpaid amount. </p>
<p style="padding-left: 30px;">Additionally, the
Act:</p>
<p style="padding-left: 30px;">Permits parties to
lengthen the time an owner has to make progress payments to a contractor from
twenty-five to seventy-five days from receipt of the GC invoice.</p>
<blockquote>
<ul>
<li>Authorizes, but restricts, retainage;</li>
<li>Imposes new procedures for change directives;</li>
<li>Permits a contractor or subcontractor to suspend performance if they have
not received timely payments;</li>
<li>For contracts in excess of $250,000, allows a contractor to ask the owner to
provide a written statement of the owner’s ability to
pay.</li>
</ul>
</blockquote>
<p><strong>II. POTENTIAL PITFALLS</strong></p>
<p>If the Act becomes law, it will significantly change important facets of the
relationship between owners, general contractors and subcontractors, and affect
the terms of construction loans. Some potentially significant obstacles these
parties are likely to face under the Act are as follows:</p>
<blockquote>
<ul>
<li>What happens if defects in the subcontractor’s work are discovered after the
owner has paid the general contractor but before the general contractor paid the
subcontractor? The Act requires general contractors to pay subcontractors
within five days of receiving payment from the owner. Can the general
contractor refuse to pay the subcontractor within five days? If the contractor
does not pay the subcontractor, who is in default? Can the general contractor
return the money to the owner?</li>
<li>Will Colorado lenders be willing coordinate with borrowers, so the lenders
will issue objections to draw requests and/or make disbursements in amounts and
within times to permit borrowers to comply with the time limits applicable for
objections and payments under the Act?</li>
<li>If an owner defaults and the lenders has taken over the project, will the
Act apply to the lender?</li>
<li>General contractors have seven days to identify, and give detailed written
notice of defects in work performed by subcontractors. Are Colorado general
contractors prepared to review and approve or deny the subcontractor’s work in
just seven days?</li>
</ul>
</blockquote>
<p>We will continue to monitor the Act and its amendments and explore its impact
on the Colorado construction industry. For now, the Act is before the Committee
on Appropriations, following recommendation by the State, Veterans, &
Military Affairs Committee. A complete copy of the Act is available for review
at: <a href="http://www.leg.state.co.us/">http://www.leg.state.co.us/</a></p>
<p> </p>
<hr />
<p><a href="http://www.fclaw.com/attorneys/bio.cfm?aid=53459">Daniel W.
Glasser</a> is Of Counsel to Fennemore Craig. He represents clients in
commercial litigation and bankruptcy, with a focus on resolving
construction-related disputes. He is licensed in Colorado, Arizona, and
Nevada. Contact Dan directly at (303) 291-3203, or <a href="mailto:dglasser@fclaw.com">dglasser@fclaw.com</a>.</p>
<p><a href="http://www.fclaw.com/attorneys/bio.cfm?aid=53511">Scott D.
McDonald</a> is an associate of Fennemore Craig, P.C. An Arizona lawyer, Scott
practices in the firm’s Phoenix and Tucson offices, with a focus on resolving
construction-related disputes. Contact Scott directly at 502-879-6827, or <a href="mailto:sdmcdona@fclaw.com">sdmcdona@fclaw.com</a>.</p>
<p><em>Fennemore Craig, P.C., is a major firm in the Southwest, with offices in
Denver, Colorado, Las Vegas, Nevada; Phoenix, Arizona; Tucson, Arizona; and
Nogales, Arizona.</em></p>
</p>
CASE ALERT—New Arizona Appellate Decision Enforces Narrow Form Indemnity Clause Against General Contractorurn:uuid:C399CA6E-E0FF-E7FE-17DF63B604EF09462008-11-25T09:11:03Z2009-09-16T09:09:00Z<p>On November 13, 2008, the Arizona Court of Appeals issued its decision in
<em>MT Builders, LLC v. Fisher Roofing, Inc.</em>, interpreting a “narrow form”
subcontract indemnity provision which reads, in part as follows: “the
[Subcontractor] shall indemnify and hold harmless [General Contractor] ... from
and against all claims . . . arising out of [Subcontractor’s] work . . .
<strong><em>to the extent</em></strong> caused in whole or in part by any
negligent act or omission of the [Subcontractor]...”. The case involved a
construction defect lawsuit filed by a condominium association against MT
Builders (MTB), the general contractor, and at least nineteen subcontractors,
including Fisher Roofing, Inc. MTB tendered defense of the case to its
subcontractors and filed cross-claims for indemnity against the subcontractors.
The subcontractors declined to defend MTB. Eventually, MTB settled the
association's claims. In turn, MTB then settled its claims against all of the
subcontractors except Fisher, the roofing subcontractor. The trial court
considered competing motions for summary judgment filed by Fisher and MTB, and
ruled in MTB’s favor on the indemnity claims, establishing $240,523 as the
portion of the settlement attributable to Fisher. The appeals court reversed and
issued three rulings that <strong><em>substantially</em></strong> impact owners,
developers, contractors and subcontractors relating to indemnity obligations on
construction projects. </p>Jeffrey Steffen
<p> </p>
<p>On November 13, 2008, the Arizona Court of Appeals issued its decision in
<em>MT Builders, LLC v. Fisher Roofing, Inc.</em>, interpreting a “narrow form”
subcontract indemnity provision which reads, in part as follows: “the
[Subcontractor] shall indemnify and hold harmless [General Contractor] ... from
and against all claims . . . arising out of [Subcontractor’s] work . . .
<strong><em>to the extent</em></strong> caused in whole or in part by any
negligent act or omission of the [Subcontractor]...”. The case involved a
construction defect lawsuit filed by a condominium association against MT
Builders (MTB), the general contractor, and at least nineteen subcontractors,
including Fisher Roofing, Inc. MTB tendered defense of the case to its
subcontractors and filed cross-claims for indemnity against the subcontractors.
The subcontractors declined to defend MTB. Eventually, MTB settled the
association's claims. In turn, MTB then settled its claims against all of the
subcontractors except Fisher, the roofing subcontractor. The trial court
considered competing motions for summary judgment filed by Fisher and MTB, and
ruled in MTB’s favor on the indemnity claims, establishing $240,523 as the
portion of the settlement attributable to Fisher. The appeals court reversed and
issued three rulings that <strong><em>substantially</em></strong> impact owners,
developers, contractors and subcontractors relating to indemnity obligations on
construction projects. </p>
<p><strong>ENFORCEMENT OF NARROW FORM INDEMNITY CLAUSES</strong></p>
<p>First and foremost, the appellate court interpreted the “narrow form”
indemnity clause to mean MTB can recover from Fisher only if MTB proves <em>at
trial</em> that its losses and expenses were caused, in whole or in part, by
Fisher’s negligence, with the recovery limited <strong><em>to the
extent</em></strong> of that causation. In short, a narrow form of indemnity
requires a trial to determine whether the indemnifying party (Fisher) is
responsible at all and, if so, the indemnified party (MTB) will be entitled to
recovery for that portion of the damages incurred in connection with the lawsuit
against it.</p>
<p><strong>INDEMNITY FOR SETTLEMENT AMOUNTS PAID</strong></p>
<p>Given that most construction defect cases are settled, the second key ruling
in <em>MT Builders</em> was that the appeals court also required MTB to
demonstrate that the amount it paid to settle the Fisher-based claims was
reasonable and prudent. The court listed a matrix of factors to be considered in
deciding reasonableness and prudence, including (1) the association's damages,
(2) the merits of the association's liability theories, (3) the merits of MTB’s
defense theories, (4) MTB’s relative fault, (5) the risks and expenses of
continued litigation, (6) any evidence of bad faith, collusion or fraud, (7) the
extent of the association's investigation and preparation of the case, and (8)
the interests of other parties. Under <em>MT Builders</em>, therefore, a party
seeking indemnity for settlement amounts paid must establish at trial that the
settlement was prudent and reasonable using a variety of factors.</p>
<p><strong>NO DUTY TO DEFEND</strong></p>
<p>The third and final important indemnity ruling is that Fisher did not have a
duty to defend MTB, upon a tender of defense, because the word “defend” was
absent from the narrow form indemnity clause at issue. The court found that the
“to the extent” language precluded a duty to defend when the duty is not
expressly provided because Fisher did not have an obligation to indemnify at all
until a determination was made about the extent of Fisher’s fault. The court
also suggested that the “to the extent” language in the indemnity may render
even an express defense obligation unenforceable because the defense obligation
could only arise after liability is established and that would be too late in
the proceedings to be a meaningful defense. Practically speaking, that ruling
means reimbursement of defense costs from the indemnifying party under narrow
form indemnity clauses will not occur until the indemnifying party’s fault has
been determined, with that degree of fault applied proportionally for
reimbursement of the indemnified party’s attorneys’ fees, legal costs and other
expenses.</p>
<p><strong>LESSONS TO BE LEARNED</strong></p>
<p>Contractors, owners and developers negotiating contracts should be aware that
under the <em>MT Builders</em> decision, the practical effects of narrow form
indemnity clauses, which limit a party’s indemnity obligations “<em><strong>to
the extent</strong></em>” of fault caused by the indemnifying party, will be to
require a trial determination of fault as a prerequisite to indemnity from the
indemnifying party. Contract negotiators concerned about reducing the potential
for litigation triggered to enforce an indemnity may wish to consider
alternative, broader forms of indemnification consistent with applicable law.
Further, before finalizing a settlement with a claimant, contractors, owners
and/or developers who intend to seek indemnity under a narrow form indemnity
clause with the requisite “to the extent” language must be careful to address
and, perhaps, document during the settlement process the various factors under
<em>MT Builders</em> relating to the reasonableness of a settlement.
Additionally, <em>MT Builders</em> demonstrates the importance of including
appropriate “defense” language in indemnity clauses, and the need to consider
how an express defense obligation may be enforced if the indemnifying party’s
obligations only arise after its liability is established. Finally, note that
this decision relates to an indemnity clause that by its terms provided
indemnity for “negligence” based claims only. Whether these principles apply to
indemnification for damages resulting from the kinds of claims not addressed in
the decision, such as contract breaches, remains to be seen. </p>
<p> </p>
Arizona Supreme Court Rules on Contract Provisions Capping Damagesurn:uuid:C3BA5E1E-D071-93FD-1633A75EE184F7992008-11-06T12:11:09Z2009-09-16T09:09:00Z<p>Professional service contracts often include provisions that limit the
service providers’ liability to the amount received under the contract. In a
decision earlier this year, the Arizona Court of Appeals ruled that, under the
Arizona constitution, the decision whether and how to enforce such provisions
must be made by the jury, rather than the judge. 1800 Ocotillo, LLC v. The WLB
Group, Inc., No. 1 CA-CV 07-0037. In reaching this conclusion, the Court of
Appeals analogized the provision to the defense of “assumption of risk,” which,
under the Arizona Constitution, must be submitted to the jury.Fennemore Craig
addressed this decision in a litigation update on February 25, 2008. In that
update we noted that, “[i]t will be challenging for defendants, seeking to rely
upon such provisions, to persuade juries to apply them in situations where the
injured party’s damages greatly exceed the limit in the contract.”</p>Christopher L. Callahan
<p>Professional service contracts often include provisions that limit the
service providers’ liability to the amount received under the contract. In a
decision earlier this year, the Arizona Court of Appeals ruled that, under the
Arizona constitution, the decision whether and how to enforce such provisions
must be made by the jury, rather than the judge. <em>1800 Ocotillo, LLC v. The
WLB Group, Inc.</em>, No. 1 CA-CV 07-0037. In reaching this conclusion, the
Court of Appeals analogized the provision to the defense of “assumption of
risk,” which, under the Arizona Constitution, must be submitted to the
jury.Fennemore Craig addressed this decision in a litigation update on February
25, 2008. In that update we noted that, “[i]t will be challenging for
defendants, seeking to rely upon such provisions, to persuade juries to apply
them in situations where the injured party’s damages greatly exceed the limit in
the contract.”
<p>The Arizona Supreme Court granted review of the Court of Appeals’ decision
and reinstated the trial court ruling, holding “that the liability-limitation
clause is neither contrary to public policy nor subject to Arizona’s
constitutional requirement that the defense of assumption of risk always be
submitted to a jury.” The underlying dispute between a developer and a survey
company alleged that the survey company was negligent in failing to identify an
existing right-of-way resulting in delays and modifications to the development.
A provision in the contract between the developer and the survey company limited
the developer’s recoverable damages for the survey company’s negligence to the
“total fees actually paid” to the survey company. The trial court granted
partial summary judgment in favor of the survey company, holding that this
provision was enforceable. The court of appeals reversed on the grounds that,
under the Arizona Constitution, issues regarding the enforcement of the
provision should have been resolved by a jury and that the trial court was wrong
in deciding the issue on summary judgment.</p>
<p>The Arizona Supreme Court disagreed with the “assumption of the risk”
analogy, stating ‘assumption of risk’ as used in [the Arizona Constitution] . .
. refer[s] only to defenses that effectively relieve the defendant of any
duty.” The Court concluded the limitation of liability clause was not such a
defense and, therefore, the issue of its validity and enforceability did not
require determination by the jury. </p>
<p>The Supreme Court also discussed the benefits of such provisions in a manner
to suggest it supported their judicial enforcement. The Court noted these
provisions “may desirably allow the parties to allocate as between themselves
the risks of damages in excess of the agreed-upon cap, which could preserve
incentives for one party to take due care while assigning the risk of greater
damages to another party that might be better able to mitigate or insure against
them.” The Supremem Court did, howvere, recognize potential defenses to the
enforceability of these provisions. Specifically, the Court noted that a cap on
damages could be challenged by showing that the parties had not negotiated the
provision, that the provision was applied in a manner contrary to the parties’
reasonable expectations, that the provision would cap damages at a dollar amount
so low as to effectively eliminate the incentive to take precautions, or that
the provision resulted from coercive or otherwise improper bargaining.</p>
<p> </p>
</p>
Bovis Strikes Back - Nevada Supreme Court Takes Mulligan On Pay-if-Paidurn:uuid:C3AD603B-A7A9-6E7A-46047FF9909F190E2008-10-31T04:10:31Z2009-09-16T09:09:00Z<p>In June, the Nevada Supreme Court released its opinion in <em>Bovis v.
Bullock</em>, 124 Nev. Adv. Op. 39, 185 P.3d 1055 (June 2008). See <a href="/construction-law/blog/post.cfm/nevada-supreme-court-decides-enforceability-of-contractual-lien-waiver-provisions" target="_blank">this
blog post</a> on the case for details of the facts. In the Court's June
opinion, it held that pay-if-pay provisions in subcontract agreements violate
Nevada public policy. Although the subcontract at issue was entered into before
the 2001 amendments to NRS Chapter 624, the Court declared in Footnote 33 that
the prompt payment sections included in the 2001 amendments render pay-if-paid
provisions unenforceable for contracts entered into after the amendments.
</p>
<p>Now, the Supreme Cout has withdrawan its June opinion and replaced it with <a href="http://www.nvsupremecourt.us/documents/advOpinions/124NevAdvOpNo92.pdf" target="_blank"><em>Bovis
v. Bullock</em>, 124 Nev. Adv. Op. 92 (Oct. 30, 2008)</a>. </p>
<p> </p>Anthony Golden
<p>In June, the Nevada Supreme Court released its opinion in <em>Bovis v.
Bullock</em>, 124 Nev. Adv. Op. 39, 185 P.3d 1055 (June 2008). See <a href="/construction-law/blog/post.cfm/nevada-supreme-court-decides-enforceability-of-contractual-lien-waiver-provisions" target="_blank">this
blog post</a> on the case for details of the facts. In the Court's June
opinion, it held that pay-if-pay provisions in subcontract agreements violate
Nevada public policy. Although the subcontract at issue was entered into before
the 2001 amendments to NRS Chapter 624, the Court declared in Footnote 33 that
the prompt payment sections included in the 2001 amendments render pay-if-paid
provisions unenforceable for contracts entered into after the amendments.
</p>
<p>Now, the Supreme Cout has withdrawan its June opinion and replaced it with <a href="http://www.nvsupremecourt.us/documents/advOpinions/124NevAdvOpNo92.pdf" target="_blank"><em>Bovis
v. Bullock</em>, 124 Nev. Adv. Op. 92 (Oct. 30, 2008)</a>. The new opinion
changes nothing with respect to pay-if-paid provisions entered into before the
2001 amendments. The Court stuck with its previous conclusion "that pay-if-paid
provisions are unenforceable because they violate public policy." The notable
difference in this new opinion, however, is in Footnote 50. There, the Court
states, "Pay-if-paid provisions entered into subsequent to the Legislature's
amendments <strong>are enforceable</strong> only in limited circumstances and
are subject to the restrictions laid out in these sections. 2001 Nev. Stat.,
ch. 341, §§ 5-6, at 1615-18." (emphasis added).</p>
<p>The statutes the Court refers to are NRS 624.624 and NRS 624.626. NRS
624.624 governs payment by higher-tiered contractors to lower-tiered
subcontractors. If there is a written agreement that includes a schedule of
payments, the statute requires payment on the due date or within 10 days of
receiveing payment for the work, whichever is earlier. If there is no payment
schedule, it reqires payment within 30 days after the lower-tiered subcontractor
submits a request for payment or within 10 days of receiving payment for the
work, whichever is earlier. NRS 624.626 provides lower-tiered subcontractors
with the ability to stop work if they have not received payment as required and
they meet certain notice prerequisites.</p>
<p>Where does this leave us? It leaves us with the following unanswered
question: what are the "limited circumstances" in which pay-if-paid provisions
entered into subsequent to the 2001 amendments are enforceable? The open
question is the benefit of this opinion over the withdrawan <em>Bovis</em>
opinion. In the former opinion, the Court conclusively said that pay-if-paid
provisions entered into after the 2001 amendments were unenforceable. Period.
But that issue was not before the Court in the case because the provision in
question was entered into before the amendments to the statutes. With this new
opinion, the Court allows itself the ability to address the question head on
when it is duly raised. It is anyone's guess how the Court will interpret NRS
624.624 and 624.626, but at least the question is open, to be answered on an
appropriate set of facts.</p>
<p> </p>
Is a Lien Claimant Entitled to Post-Judgment Attorney Fees?urn:uuid:C39ECB0F-A567-514E-46DA68F5A9D4D0FD2008-10-21T12:10:27Z2009-09-16T09:09:00Z<p>In <em>Carl B. Barney v. Mt. Rose Heating & Air Conditioning</em>, 124
Nev. Adv. Op. 71 (Sept. 18, 2008), the Nevada Supreme Court addressed, among
other things: (1) whether NRS 108.237(1), which allows for recovery of
attorney’s fees in a mechanic’s lien action, covers all fees incurred to enforce
the mechanic’s lien, including those post-judgment attorney fees incidental to
the lien’s enforcement through foreclosure; and (2) whether the district court
erred in denying a post-judgment motion to enter satisfaction of the judgment
because not all of the attorney fees were paid. Carl B. Barney
(“<em>Barney</em>”) contracted with Reno Construction, Inc. (“<em>RCI</em>”) to
renovate his house. RCI subcontracted with Mt. Rose Heating & Air
Conditioning (“<em>Mt. Rose</em>”) to provide equipment and services as part of
the renovations. Barney refused to pay for the work, which he determined was
defective, and RCI and Mt. Rose filed mechanic’s liens against the property.
Both RCI and Mt. Rose obtained judgments and decrees of foreclosure against
Barney. Mt. Rose, prior to any foreclosure sale, garnished funds Barney held in
a bank, and attempted to execute upon Barney’s personal property. Barney filed
and won a motion to exempt his bank account from execution and to quash the
garnishment. Mt. Rose sought supplemental attorney fees and costs (“<em>First
Mt. Rose Motion</em>”); the court granted their request. Later, Mt. Rose filed
a supplemental motion (“<em>Second Mt. Rose Motion</em>”), seeking fees for
post-judgment matters, including the judgment’s execution, the garnishment, and
the release of Barney’s bank funds. </p>Jeffrey Steffen
<p> </p>
<p>In <em>Carl B. Barney v. Mt. Rose Heating & Air Conditioning</em>, 124
Nev. Adv. Op. 71 (Sept. 18, 2008), the Nevada Supreme Court addressed, among
other things: (1) whether NRS 108.237(1), which allows for recovery of
attorney’s fees in a mechanic’s lien action, covers all fees incurred to enforce
the mechanic’s lien, including those post-judgment attorney fees incidental to
the lien’s enforcement through foreclosure; and (2) whether the district court
erred in denying a post-judgment motion to enter satisfaction of the judgment
because not all of the attorney fees were paid. Carl B. Barney
(“<em>Barney</em>”) contracted with Reno Construction, Inc. (“RCI”) to renovate
his house. RCI subcontracted with Mt. Rose Heating & Air Conditioning
(“<em>Mt. Rose</em>”) to provide equipment and services as part of the
renovations. Barney refused to pay for the work, which he determined was
defective, and RCI and Mt. Rose filed mechanic’s liens against the property.
Both RCI and Mt. Rose obtained judgments and decrees of foreclosure against
Barney. Mt. Rose, prior to any foreclosure sale, garnished funds Barney held in
a bank, and attempted to execute upon Barney’s personal property. Barney filed
and won a motion to exempt his bank account from execution and to quash the
garnishment. Mt. Rose sought supplemental attorney fees and costs (“<em>First
Mt. Rose Motion</em>”); the court granted their request. Later, Mt. Rose filed
a supplemental motion (“<em>Second Mt. Rose Motion</em>”), seeking fees for
post-judgment matters, including the judgment’s execution, the garnishment, and
the release of Barney’s bank funds. </p>
<p>While this <a href="/construction-law/blog/">supplemental motion</a>
was before the court, Barney paid Mt. Rose an amount to satisfy the judgment and
the attorney fees and costs awarded in the First Mt. Rose Motion; however, Mt.
Rose refused to recognize the judgment as fully satisfied. Barney moved the
district court for an order directing the clerk to enter satisfaction of the
judgment. Mt. Rose opposed the motion, asserting it was willing to provide a
partial satisfaction, but was entitled to additional awards of attorney fees
(requested in the Second Mt. Rose Motion), and the court denied the motion.
Just over three (3) weeks after denying Barney’s motion, the court granted the
Second Mt. Rose Motion for fees and costs. Barney appealed the post-judgment
orders, arguing that the court was not authorized to award attorney fees
incurred after the original judgment, and, even if authorized, the fees were
unreasonable. Barney also argued the district court should have directed the
clerk to enter the judgment’s satisfaction. The Court held that NRS 108.237(1)
covers not only pre-judgment fees and costs, but also costs and fees that are
incidental to the lien’s enforcement. Since the enforcement action ends only
when the property is sold and the proceeds are distributed (or otherwise paid)
and the lien is discharged or released, costs and fees up to this point are
properly awarded (so long as they are incidental to the lien’s enforcement).
Additionally, the Court held that since Mt. Rose had a motion for attorney fees
pending at the time Barney tendered payment for the judgment, Barney was only
entitled to partial satisfaction of judgment, and affirmed the finding of the
district court.</p>
<p> </p>
Nevada Supreme Court Clarifies its Definition of a "New Residence" for NRS Chapter 40urn:uuid:C3A07E0E-FB58-03D8-1BC4D7B16D2F6A9B2008-10-20T10:10:06Z2009-09-16T09:09:00Z<p>In <em>ANSE, Inc., d/b/a Nevada State Plastering v. The Eighth Judicial
District Court</em>, 124 Nev. Adv. Op. 74 (Sept. 25, 2008), the Nevada Supreme
Court clarified whether their definition of a “new residence”, as decided in
Westpark Owners’ Ass’n v. District Court (123 Nev. ___, 167 P.3d 421 (2007); <a href="/construction-law/blog/post.cfm/court-defines-new-residence-and-addresses-buyer-waivers-of-constructional-defect-claims">see
blog post from June 27, 2008</a>), precluded a homeowner who is not the home’s
first purchaser from seeking remedies available under NRS Chapter 40 for
constructional defects. In Westpark, the Court interpreted “new residence” as a
product of original construction that has been unoccupied as a dwelling from the
completion its construction until its sale. In this case, approximately 700 of
the residences at issue in the constructional defect case were occupied as
dwellings before the residences’ subsequent owners obtained title to the homes.
Relying on Westpark, petitioners sought summary judgment as to their NRS Chapter
40 liability on claims related to those residences.</p>Jeffrey Steffen
<p>In <em>ANSE, Inc., d/b/a Nevada State Plastering v. The Eighth Judicial
District Court</em>, 124 Nev. Adv. Op. 74 (Sept. 25, 2008), the Nevada Supreme
Court clarified whether their definition of a “new residence”, as decided in
Westpark Owners’ Ass’n v. District Court (123 Nev. ___, 167 P.3d 421 (2007); <a href="/construction-law/blog/post.cfm/court-defines-new-residence-and-addresses-buyer-waivers-of-constructional-defect-claims">see
blog post from June 27, 2008</a>), precluded a homeowner who is not the home’s
first purchaser from seeking remedies available under NRS Chapter 40 for
constructional defects. In Westpark, the Court interpreted “new residence” as a
product of original construction that has been unoccupied as a dwelling from the
completion its construction until its sale. In this case, approximately 700 of
the residences at issue in the constructional defect case were occupied as
dwellings before the residences’ subsequent owners obtained title to the homes.
Relying on Westpark, petitioners sought summary judgment as to their NRS Chapter
40 liability on claims related to those residences.
</p>
<p>The Court found that petitioner’s expansion of “new residence” in Westpark as
precluding a homeowner who is not the home’s original purchaser from obtaining
remedies available under NRS Chapter 40 violates that chapter’s spirit, leads to
unreasonable and absurd results, and ignores Westpark’s unique factual
background. While rejecting petitioner’s claim, the Court recognized it needed
to better clarify the definition of “new residence”. The Court indicated a “new
residence” under NRS 40.615 is one that has remained unoccupied as a dwelling
from the completion of its construction to the point of its first sale.
Thereafter, subsequent owners of that residence, as claimants, may seek NRS
Chapter 40’s residential constructional defect remedies, so long as the action
is instituted within the applicable statute of repose.</p>
<p> </p>
Court Holds Discretionary Immunity Protects Governmental Entity from Tort Liability in Accepting or Rejecting Bids for Public Works Projectsurn:uuid:C3B5C1B6-E1A8-F3FB-5BD1854276FCAB562008-10-17T06:10:47Z2009-09-16T09:09:00Z<p>The Nevada Supreme Court held recently that a Boulder City engineer's
requirement that a low-bidding general contractor replace a particular
subcontractor before the City would accept the bid was an action falling under
discretionary immunity and precluded liability against the City for tortious
interference of the subcontractor's contract. City of Boulder City v. Boulder
Excavating, Inc., 124 Nev. Adv. Op. 65 (Sept. 11, 2008). Over a period of
several years, Boulder Excavating, Inc. ("BEI"), as a general contractor,
secured several accepted bids with Boulder City for public works projects. In
2000, however, a dispute between BEI and Boulder City over a road construction
project occurred and was resolved by protracted arbitration proceedings, after
which both parties claimed to have prevailed.</p>Anthony Golden
<p>The Nevada Supreme Court held recently that a Boulder City engineer's
requirement that a low-bidding general contractor replace a particular
subcontractor before the City would accept the bid was an action falling under
discretionary immunity and precluded liability against the City for tortious
interference of the subcontractor's contract. <em>City of Boulder City v.
Boulder Excavating, Inc.</em>, 124 Nev. Adv. Op. 65 (Sept. 11, 2008). Over a
period of several years, Boulder Excavating, Inc. ("BEI"), as a general
contractor, secured several accepted bids with Boulder City for public works
projects. In 2000, however, a dispute between BEI and Boulder City over a road
construction project occurred and was resolved by protracted arbitration
proceedings, after which both parties claimed to have prevailed.
</p>
<p>In late
2000 or early 2001, Boulder City solicited bids for the multimillion dollar
Veteran's Memorial Park public works project. McComb Construction, a general
contractor, submitted the lowest responsive and responsible bid. McComb's bid,
however, included BEI as a subcontractor. Boulder City's engineer, Scott
Hansen, requested that McComb seek permission to replace BEI with another
subcontractor before accepting McComb's bid. McComb complied with the request,
and the City awarded McComb the project.<br /><br />BEI then brought suit against
Boulder City and Hansen for, among other things, (1) intentionally interfering
with the contractual relationship between McComb and BEI; (2) conspiring to
evade the public bidding requirements of NRS Chapter 338; and (3) denying BEI of
its rights to perform subcontract work. BEI's claims against Boulder City were
based on Hansen's conduct as Boulder City's primary government actor. The
district court found that Hansen was immune as a governmental actor under NRS
41.032(2). However, despite Hansen's immunity and that the claims against
Boulder City were based on Hansen's actions, the court did not find Boulder City
immune.<br /><br />On appeal, the Nevada Supreme Court concluded that the district
court erred. If Hansen was protected by NRS 41.032(2)'s discretionary immunity
as a governmental actor, the agency for which he acted was also protected.
Accordingly, the Supreme Court held that Boulder City was also immune because
"Hansen was engaged in discretionary acts as defined by NRS 41.032(2), and
because he was acting pursuant to his statutory authority in selecting
subcontractors under NRS 338.141."<br /><br /><strong>A potential footnote
landmine:</strong><br />In footnote 22, the Supreme Court addresses an argument of
BEI that immunity should not be extended to Boulder City on BEI's claim of
intentional inference with contract because "governmental actors are not
entitled to immunity for illegal intentional acts or acts taken in bad faith."
In addressing this argument, the Court concluded that because Boulder City had
not accepted McComb's bid at the time of Hansen's actions, there was no contract
with which to interfere. "[A] putative subcontractor named in a public works
bid has no protected property interest in the public works contract because no
cognizable claim to damages can arise before an award is made." In reaching
this conclusion, the Court rejected BEI's argument under <em>Clark Pacific v.
Krump Constr., Inc., 942</em> F. Supp. 1324 (D. Nev. 1996).<br /><br />In <em>Clark
Pacific</em>, the Nevada Federal District Court concluded that a "psuedo
contract" exists between the general contractor and a subcontractor
<em>after</em> the public entity awards the project to the general but before a
formal contract is signed between the general and the sub. The <em>Clark
Pacific</em> court did not address BEI's argument on the issue of whether some
sort of contractual relationship exists between the general and the sub before
the public entity awards the contract to the general. Therefore, the Nevada
Supreme Court is correct that <em>Clark Pacific</em> does not apply to BEI
because BEI was substituted before Boulder City had awarded the contract to
McComb. The Court, however, did not need to go so far as to say that, for a
subcontractor, "no cognizable claim to damages can arise before an award is
made." The Court's statement forecloses any possible claim for damages by a
subcontractor before the public entity awards project. Depending on future
cases that come before the Court, this may become one of those footnotes that
the Court retreats from and limits to the facts of this case.<br /><br />For a full
copy of the case: <a href="http://www.nvsupremecourt.us/documents/advOpinions/124NevAdvOpNo65.pdf">http://www.nvsupremecourt.us/documents/advOpinions/124NevAdvOpNo65.pdf</a>.</p>
<p> </p>
Contractor's License is Intangible Personal Property that is Subject to a Claim for Conversionurn:uuid:C3B4281C-0DA3-6B6B-C765703AB14C80632008-10-17T06:10:50Z2009-09-16T09:09:00Z<p>In <em>M.C. Multi-Family Dev. v. Crestdale Assoc.</em>, 124 Nev. Adv. Op. No.
77 (Oct. 2, 2008), the Nevada Supreme Court concluded that a contractor's
license is the personal property of the entity or individual named on the
license. Therefore, it is subject to a claim of conversion if another entity or
individual exercises "wrongful dominion" over the license. The qualifying
employee of Walter Homes, Ltd. used Walter Homes' contractor's license to
develop real property under a separate company, Crestdale Associates, Ltd.,
without the permission of the majority interest owners of Walter Homes. During
trial, after the plaintiff's case in chief, the district court entered a
directed verdict against the plaintiff's conversion claim. The district court
found that Crestdale Associates had not "taken" the license.</p>Anthony Golden
<p>In <em>M.C. Multi-Family Dev. v. Crestdale Assoc.</em>, 124 Nev. Adv. Op. No.
77 (Oct. 2, 2008), the Nevada Supreme Court concluded that a contractor's
license is the personal property of the entity or individual named on the
license. Therefore, it is subject to a claim of conversion if another entity or
individual exercises "wrongful dominion" over the license. The qualifying
employee of Walter Homes, Ltd. used Walter Homes' contractor's license to
develop real property under a separate company, Crestdale Associates, Ltd.,
without the permission of the majority interest owners of Walter Homes. During
trial, after the plaintiff's case in chief, the district court entered a
directed verdict against the plaintiff's conversion claim. The district court
found that Crestdale Associates had not "taken" the license.
</p>
<p>On appeal,
the Nevada Supreme Court determined first that a contractor's license embodies
the intangible rights of the entity or person named on the license, and it is
therefore intangible personal property subject to a conversion claim under
Nevada law. Second, the Court concluded that a claimant for conversion of a
contractor's license need not establish a physical "taking" of the license.
"While the unauthorized use of a contractor's license does not involve an actual
physical appropriation or 'taking' as the district court concluded, it
nonetheless may constitute an act inconsistent with the rights of the
titleholder. . . ." Accordingly, the Court reversed the district court's
directed verdict and remanded the case for a jury trial on the conversion
claim.<br /> <br /><strong>Note to qualified employees:</strong><br />The Court
specifically held that a person's status as the qualified employee does not give
that person an "ownership or possessor interest in the corporate contractor's
license and . . . such license can only be used by the individual or entity to
which it is issued."</p>
<p> </p>
Contractor Liability Under Implied Warranties in Residential Constructionurn:uuid:C3B297AA-BC0B-583F-C6C6C7752498C3DC2008-08-30T01:08:16Z2009-09-16T09:09:00Z<p>The Arizona Supreme Court recently ruled that homeowners (and homeowner
associations on behalf of homeowners) may sue residential homebuilders on an
implied warranty of workmanship and habitability even if the homebuilder was not
also the vendor of the homes and the homebuilder had no other direct
relationship with the homebuyer. <em>See The Lofts at Fillmore Condominium
Assoc. v. Reliance Commercial Construction</em>, No. CV-07-0416-PR (Ariz. filed
Aug. 19, 2008) (<a href="http://www.supreme.state.az.us/opin/pdf2008/ACV070416PR.pdf">http://www.supreme.state.az.us/opin/pdf2008/ACV070416PR.pdf</a>).
</p>
<p><br /><strong>How
does this work in Nevada?<br /></strong>Nevada has not addressed the situation at
issue in Arizona's <em>Lofts at Fillmore</em> case where the homebuilder was not
also the vendor or a joint venturer with the vendor of the homes. The Nevada
Supreme Court, however, has held that where a homebuilder is a joint venturer
with the vendor, both the homebuilder and the vendor are jointly and severally
liable to the homebuyer for breach of the implied warranty of habitability.
<em>See Radaker v. Scott</em>, 109 Nev. 653, 855 P.2d 1037 (1993).</p>
<p> </p>Anthony Golden
<p> </p>
<p>The Arizona Supreme Court recently ruled that homeowners (and homeowner
associations on behalf of homeowners) may sue residential homebuilders on an
implied warranty of workmanship and habitability even if the homebuilder was not
also the vendor of the homes and the homebuilder had no other direct
relationship with the homebuyer. <em>See The Lofts at Fillmore Condominium
Assoc. v. Reliance Commercial Construction</em>, No. CV-07-0416-PR (Ariz. filed
Aug. 19, 2008) (<a href="http://www.supreme.state.az.us/opin/pdf2008/ACV070416PR.pdf">http://www.supreme.state.az.us/opin/pdf2008/ACV070416PR.pdf</a>).<br /><br /><strong>How
does this work in Nevada?<br /></strong>Nevada has not addressed the situation at
issue in Arizona's <em>Lofts at Fillmore</em> case where the homebuilder was not
also the vendor or a joint venturer with the vendor of the homes. The Nevada
Supreme Court, however, has held that where a homebuilder is a joint venturer
with the vendor, both the homebuilder and the vendor are jointly and severally
liable to the homebuyer for breach of the implied warranty of habitability.
<em>See Radaker v. Scott</em>, 109 Nev. 653, 855 P.2d 1037 (1993).<br /><br />Here
is what we know under Nevada law: (1) A hombuilder that is also a vendor is
liable to a homebuyer for breach of the implied warranty of habitability. (2) A
homebuilder that joint ventures with the vendor is liable to a homebuyer for
breach of the implied warranty. The Nevada Supreme Court in <em>Radaker</em>
extensively discussed the history of the implied warranty of habitability as
being based in public policy. The Court agreed with numerous other courts that
the implied warranty was based on sound public policy: "We agree with the
virtual consensus among courts in our sister states that the implied warranty of
habitability reflects a naturally expected and sound public policy."
<em>Radaker</em>, 109 Nev. at 661, 855 P.2d at 1042. The Court then adopted the
implied warranty for Nevada. <em>Id</em>.<br /><br />By basing the implied warranty
of habitability on public policy rather than on contract, the <em>Radaker</em>
decision provides a stepping stone for the Nevada Supreme Court to go down the
path of Arizona and extend the implied warranty when there is no contractual
privity between the homebuilder and the homebuyer. The Arizona court in
<em>Lofts at Fillmore</em> also based its decision to extend the implied warrant
on public policy grounds. "We stressed in <em>Richards</em> that, given the
policies behind the implied warranty – to protect innocent buyers and hold
builders responsible for their work – any reasoning which would arbitrarily
interpose a first buyer as an obstruction to someone equally deserving of
recovery is incomprehensible." <em>Lofts at Fillmore</em> at 9-10 (internal
quotations and citations omitted). It is not unthinkable then for Nevada to go
one more step like Arizona has and hold that a homebuilder can be liable to a
homebuyer for breach of the implied warranty even if the homebuilder is merely a
contractor of the vendor and has no direct relationship with the homebuyer and
gains no direct benefit from the sale of the home. We'll have to wait and see
when such a case presents itself to the Nevada Supreme Court.<br /><br />Regardless
of how loosely Nevada may in the future apply the implied warranty of
habitability, any claims based on the implied warranty by a homebuyer would
almost certainly be subject to the requirements of Nevada's construction defect
statutes (NRS 40.600 - 40.695). Therefore, at a minimum, a homebuilder would
have to be given notice of the defect and an opportunity to cure it before an
action can be commenced by a homebuyer. </p>
<p> </p>
Contractors Must use E-Verify to Verify Workers Employment Eligibility for all Future Federal Contractsurn:uuid:C3B0E9CD-FF3B-D072-A17F5CC6DFAC9F492008-07-09T01:07:21Z2009-09-16T09:09:00Z<p>On June 6, 2008, President Bush issued an <a href="http://www.whitehouse.gov/news/releases/2008/06/20080609-2.html">Executive
Order</a> amending Executive Order 12989, which directs all Federal departments
and agencies to require contractors, as a condition of each future federal
contract, to agree to use an electronic employment eligibility verification
system (designated by the Secretary of Homeland Security) to verify the
employment eligibility of: (1) all persons hired during the contract term by the
contractor to perform employment duties within the United States; and (2) all
persons assigned by the contractor to perform work within the United States on
the federal contract.</p>Anthony Golden
<p>On June 6, 2008, President Bush issued an <a href="http://www.whitehouse.gov/news/releases/2008/06/20080609-2.html">Executive
Order</a> amending Executive Order 12989, which directs all Federal departments
and agencies to require contractors, as a condition of each future federal
contract, to agree to use an electronic employment eligibility verification
system (designated by the Secretary of Homeland Security) to verify the
employment eligibility of: (1) all persons hired during the contract term by the
contractor to perform employment duties within the United States; and (2) all
persons assigned by the contractor to perform work within the United States on
the federal contract.
<p><br />The Department of Homeland Security recently
designated E-Verify as the electronic employment eligibility verification system
to be used pursuant to Executive Order 12989.<br /><br />For more detailed
information see <a href="http://www.fclaw.com/newsletter/materials/Immigration_Update_6-18-08.pdf">here</a>.<br /><br />E-Verify
can be accessed through the <a href="http://www.dhs.gov/xprevprot/programs/gc_1185221678150.shtm">Department
of Homeland Security's website</a>. </p>
</p>
Nevada Supreme Court Decides Enforceability of Contractual Lien Waiver Provisionsurn:uuid:C3AEFFD1-A8CF-D13A-37BB1E1A0FD003C22008-06-28T01:06:27Z2009-09-16T09:09:00Z<p>The Nevada Supreme Court recently addressed two issues of concern to
contractors and owners: (1) the enforceability of lien waiver provisions, and
(2) the enforceability of pay-if-paid provisions. <span style="font-style: italic;">Lehrer McGovern
Bovis, Inc. v. Bullock Insulation, Inc.</span>, 124 Nev. Adv. Op. 39 (June
2008), is the latest saga from the Venetian mechanics' lien lawsuits. The case
involved the owner and general contractor attempting to foil a subcontractor's
lien foreclosure and breach of contract claims by asserting a lien waiver
provision and a pay-if-paid provision in the subcontract agreement<span style="font-style: italic;">. </span>The Court
declared that Nevada's public policy "favor[s] contractors' rights to secured
payment for labor, materials, and equipment furnished." Based on this policy,
the Court struck down both the lien waiver provision and the pay-if-paid
provision. The subcontract agreement at issue predated the legislative
amendments to the mechanics' lien statutes, NRS Chapter 108, requiring specific
forms for lien waivers and predated the amendments to NRS Chapter 624, which
created Nevada's prompt payment statutes. Although not at issue, the Court
thought it necessary to state, without explanation or analysis in what will
become known as the infamous Footnote 33, that the amendments to Chapter 624
creating the prompt pay statutes, "make pay-if-paid provisions entered into
subsequent to the Legislature's amendments unenforceable."<span style="font-size: 100%;"><br /></span></p>Anthony Golden
<p>The Nevada Supreme Court recently addressed two issues of concern to
contractors and owners: (1) the enforceability of lien waiver provisions, and
(2) the enforceability of pay-if-paid provisions. <span style="font-style: italic;">Lehrer McGovern
Bovis, Inc. v. Bullock Insulation, Inc.</span>, 124 Nev. Adv. Op. 39 (June
2008), is the latest saga from the Venetian mechanics' lien lawsuits. The case
involved the owner and general contractor attempting to foil a subcontractor's
lien foreclosure and breach of contract claims by asserting a lien waiver
provision and a pay-if-paid provision in the subcontract agreement<span style="font-style: italic;">. </span>The Court
declared that Nevada's public policy "favor[s] contractors' rights to secured
payment for labor, materials, and equipment furnished." Based on this policy,
the Court struck down both the lien waiver provision and the pay-if-paid
provision. The subcontract agreement at issue predated the legislative
amendments to the mechanics' lien statutes, NRS Chapter 108, requiring specific
forms for lien waivers and predated the amendments to NRS Chapter 624, which
created Nevada's prompt payment statutes. Although not at issue, the Court
thought it necessary to state, without explanation or analysis in what will
become known as the infamous Footnote 33, that the amendments to Chapter 624
creating the prompt pay statutes, "make pay-if-paid provisions entered into
subsequent to the Legislature's amendments unenforceable."
</p>
<p><span style="font-size: 100%;"><span style="font-size: 100%;"><br /></span></span><span style="font-weight: bold; font-size: 100%;">Mechanics' Lien
Waivers</span><br />The subcontract agreement between subcontractor Bullock
Insulation and general contractor Bovis incorporated a provision from the
general conditions in which Bullock Insulation promised "'not [to] suffer or
permit any lien or other encumbrance to be filed' against the project." The
Court noted that the "lien waiver provision applies regardless of whether
Bullock Insulation received any payment" and therefore concluded that "such
provision violates public policy, as it fails to secure payment for Bullock
Insulation."<br /><br />The Court assured that not every lien waiver provision
violates public policy and that the enforceability of a lien waiver clause must
be decided on a case-by-case basis. Limiting the enforceability of lien waiver
provisions to the facts of each case seems like a fair result, but the Court
gave no guidance as to what types of lien waiver provisions would be enforceable
without payment in full. The public policy proclamation coupled with NRS
108.2453(1), which prohibits the waiver of mechanics' lien rights unless the
appropriate forms specified in Chapter 108 are completed and payment made,
suggest that without payment in full, mechanics' lien rights can not be
waived.<br /><br /><span style="font-weight: bold; font-size: 100%;">Pay-If-Paid
Provisions</span><br />More disturbing than the Court's treatment of the lien
waiver provision is its decision on the pay-if-paid provision. The subcontract
agreement contained a pay-if-paid provision whereby Bullock Insulation's right
to payment for its work was contingent upon payment by the owner to Bovis. The
Court held the provision unenforceable because "a pay-if-paid provision limits a
subcontractor's ability to be paid for work already performed" and therefore
"such a provision impairs the subcontractor's statutory right to place a
mechanic's lien on the construction project." Rather than limit the holding to a
case-by-case analysis, however, the Court concluded that all pay-if-paid
provisions that were entered into before the amendments to NRS Chapter 624 are
unenforceable.<br /><br />What's more, in Footnote 33, the Court proclaimed,</p>
<blockquote>We note that in 2001, the Legislature amended NRS Chapter 624 to
include prompt payment provisions contained in NRS 624.624 through 624.626,
which <span style="font-style: italic;">make
pay-if-paid provisions entered into subsequent to the Legislature's amendments
unenforceable</span>. (emphasis added).<br /></blockquote>
<p>The Court acknowledged that the amendment to Chapter 624 "does not affect our
analysis here because it is not retroactive." Yet, the Court rang the bell
anyway.<br /><br />A major problem with Footnote 33 is that the prompt payment
statutes in Chapter 624 do not render pay-if-paid clauses unenforceable. In
fact, NRS 624.626(1)(b) recognizes that pay-if-paid or pay-when-paid provisions
regularly exist in subcontract agreements and grants the subcontractor the
remedy of stopping work when a higher-tiered contractor does not timely pay a
lower-tiered contractor even if the higher-tiered contractor has not been paid
by the owner. Additionally, pay-if-paid provisions do not necessarily eliminate
a subcontractor's mechanic's lien rights. Even with a pay-if-paid provision in a
subcontract agreement, the subcontractor remains able perfect and foreclose on
its mechanic's lien against the owner. Despite these remedies, Footnote 33
effectively makes the general contractor a lender of the owner by requiring
general contractors to pay subcontractors when the general has not received
payment from the owner. This is true even if the subcontractor has assumed the
risk of nonpayment by agreeing to a pay-if-paid provision.<br /><br /><span style="font-weight: bold; font-size: 100%;">Where To Go From
Here</span><br />Undoubtedly, the <span style="font-style: italic;">Bovis</span> decision will draw a lot of
criticism. A motion for rehearing would not be surprising. The decision makes it
more important than ever for general contractors to verify the financial
viability of owners to complete a project. So far, the decision appears
favorable to subcontractors that are subject to now-unenforceable lien waiver
and pay-if-paid provisions. Owners should expect post-<span style="font-style: italic;">Bovis</span>
contracts to attempt to allocate more heavily to the owner the general
contractor's risk of liability to subcontractors for owner nonpayment. But even
a reallocation of risk cannot protect a general contractor from an insolvent
owner. </p>
<p> </p>
Does NRS Chapter 40 Apply to Completed Blueprints for an Unfinished Residence?urn:uuid:C39564FF-A81B-5DA9-8158C137D77370C02008-06-27T08:06:52Z2009-09-16T09:09:00Z<p>The quick answer is "No". In Pankopf v. Peterson, ___ Nev. ___, 175 P.3d 910
(2008), the Pankopfs entered into a contract with Peterson for residential
design and drawing services for a personal residence. Peterson provided
blueprints for a personal residence, and excavation for the residence’s
construction began. The plans failed to identify the types of trees that would
be planted on the site as required by the Pankopf’s homeowner’s association, and
the excavation process was halted. According to the Pankopfs, a number of
deficiencies in Peterson's work ultimately prevented them from building their
residence. The Pankopfs brought suit against Peterson, alleging that Peterson's
plans contained numerous design defects, mistakes, omissions, and inaccuracies
that prevented them from constructing the residence. Peterson subsequently filed
a motion to dismiss under NRCP 12(b)(5), arguing that the Pankopfs failed to
comply with certain requirements set forth in NRS Chapter 40 that applied in
constructional defect cases. The Pankopfs argued that they did not make a claim
for relief based on any constructional defect within the scope of NRS Chapter
40.</p>Jeffrey Steffen
<p> </p>
<p>The quick answer is "No". In Pankopf v. Peterson, ___ Nev. ___, 175 P.3d 910
(2008), the Pankopfs entered into a contract with Peterson for residential
design and drawing services for a personal residence. Peterson provided
blueprints for a personal residence, and excavation for the residence’s
construction began. The plans failed to identify the types of trees that would
be planted on the site as required by the Pankopf’s homeowner’s association, and
the excavation process was halted. According to the Pankopfs, a number of
deficiencies in Peterson's work ultimately prevented them from building their
residence. The Pankopfs brought suit against Peterson, alleging that Peterson's
plans contained numerous design defects, mistakes, omissions, and inaccuracies
that prevented them from constructing the residence. Peterson subsequently filed
a motion to dismiss under NRCP 12(b)(5), arguing that the Pankopfs failed to
comply with certain requirements set forth in NRS Chapter 40 that applied in
constructional defect cases. The Pankopfs argued that they did not make a claim
for relief based on any constructional defect within the scope of NRS Chapter
40. </p>
<p>The district court granted Peterson's motion, concluding that because NRS
40.615 defines a constructional defect as a “defect in the design ... of an
alteration of or addition to an existing residence, or of an appurtenance” and
NRS 40.605 defines an appurtenance as including “the parcel of real property,”
the Pankopf’s claims fell within NRS Chapter 40's purview. The Court, on appeal,
stated that because no residence existed, the parcel of real property cannot
constitute an appurtenance within the meaning of NRS 40.605. In addition, the
Pankopfs primarily complained of mistakes in Peterson's plans for their house,
not in the design of any appurtenance. Therefore, the Court concluded that the
Pankopf’s claims did not fall under NRS Chapter 40 based on the plain language
of the definitions set forth in NRS 40.615 and NRS 40.605(1). The Court also
addressed the meaning of the term “new residence” as defined by NRS Chapter 40,
citing their recent decision in Westpark Owners' Ass'n v. District Court (see
below). Specifically, the Court held that “a residence is ‘new’ when it is a
product of original construction that has been unoccupied as a dwelling from the
completion of its construction until the point of sale.” Since the Pankopf’s
residence has not been completed, it cannot constitute a “new residence” for the
purposes of NRS Chapter 40. As such, NRS Chapter 40 does not apply to completed
blueprints for unfinished residences.</p>
<p> </p>
Court Defines New Residence and Addresses Buyer Waivers of Constructional Defect Claimsurn:uuid:C3926C4C-D5BB-6BFD-5A6362A5CCC684AD2008-06-27T08:06:03Z2009-09-16T09:09:00Z<p>In <em>Westpark Owners’ Association v. Eighth Judicial District Court</em>,
___ Nev. ___, 167 P.3d 421 (2007), the Court addressed three (3) issues
concerning NRS Chapter 40 (constructional defects): i) the definition of
“residence”; ii) the definition of “new”, in the context of a residence; and
iii) the effect of a general waiver of constructional defects in a sales
contract. Westpark Associates, LLC (“<em>Westpark</em>”) purchased a partially
completed condominium project out of bankruptcy, and completed an additional 108
units, but due to market conditions decided to lease the 108 units as
apartments, and did so from 1997 through 2003. Westpark started selling the
units to the general public, and each contract required the buyer to waive “any”
possible construction defect claims. The converted condo owners began
experiencing problems with their units, and the Westpark Owners’ Association
(the “<em>Association</em>”) served Westpark with a formal Chapter 40 notice.
</p>Jeffrey Steffen
<p>In <em>Westpark Owners’ Association v. Eighth Judicial District Court</em>,
___ Nev. ___, 167 P.3d 421 (2007), the Court addressed three (3) issues
concerning NRS Chapter 40 (constructional defects): i) the definition
of “residence”; ii) the definition of “new”, in the context of a
residence; and iii) the effect of a general waiver of constructional
defects in a sales contract. Westpark Associates, LLC (“<em>Westpark</em>”)
purchased a partially completed condominium project out of bankruptcy,
and completed an additional 108 units, but due to market conditions
decided to lease the 108 units as apartments, and did so from 1997
through 2003. Westpark started selling the units to the general public,
and each contract required the buyer to waive “any” possible
construction defect claims. The converted condo owners began
experiencing problems with their units, and the Westpark Owners’
Association (the “<em>Association</em>”) served Westpark with a formal
Chapter 40 notice. </p>
<p>The district court entered partial summary judgment
in favor of Westpark, declaring generally that Westpark had “no
liability” in connection with the development or sale, relying on
several conclusions of law which were revisited by the Nevada Supreme
Court. </p>
<p>First, contrary to the district court’s reasoning, the Court
found that the mere fact the units were originally built as apartments
does not prevent them from meeting the definition of a residence. The
Court found the event conferring “residence” status is the transfer of
title to a home purchaser. Second, the Court interpreted “new” as a
product of original construction that has been unoccupied as a dwelling
from the completion its construction until its sale. Although the units
in this matter did not meet the definition of “new”, the Court found
that if Westpark altered or repaired the units before their sale, they
would fall under NRS 40.615. </p>
<p>Finally, while NRS 40.640(5) allows a
contractor and homebuyer to stipulate to a waiver of any potential
claims under NRS Chapter 40, the “waived” constructional defect must be
disclosed to the buyer in clear language before the purchase of the
residence. Here, the waivers did not disclose any constructional
defects; they stated only that certain defects “may” exist and listed a
number of potential defects. This general disclaimer language was not
sufficient to waive any claims pursuant to NRS Chapter 40.</p>
Court Creates Reasonable Threshold Test For Constructional Defect Pre-Litigation Noticesurn:uuid:C3905461-D0E7-D0C4-E66CDA9A0BC4F7EF2008-06-27T08:06:23Z2009-09-16T09:09:00ZJeffrey Steffen
<p>In D.R. Horton v. Eighth Judicial District Court, ___ Nev. ___, 168 P.3d 731 (2007), D.R. Horton, Inc. (“<em>D.R. Horton</em>”) constructed 414 residences in 138 buildings in the First Light at Boulder Ranch Community in Henderson, Nevada (“<em>First Light</em>”).
Believing that numerous constructional defects may exist in each
residence, First Light hired experts to assist it in preparing an NRS
40.645 pre-litigation notice of constructional defects. The notice was
formulated after using visual and invasive testing in a small
representative sampling of homes in the community. First Light did not
provide D.R. Horton with the addresses or the expert report of the
homes that were tested. Using the information they found, the First
Light experts simply extrapolated the percentage of homes in which they
believed each defect existed throughout the community. D.R. Horton
moved the district court for a declaratory judgment, stating that First
Light’s NRS 40.645 notice was unreasonable and thus statutorily
insufficient. The district court denied the motion, and D.R. Horton
filed a writ petition challenging the district court’s order. To
address the problem of what satisfies the “reasonable detail”
requirement of NRS 40.645, the Court formulated the “reasonable
threshold” test to be used when pre-litigation notices contain
extrapolated data. The scope of the extrapolated notice must be narrow.
</p>
<p>First, the homeowner’s expert must test and verify the existence of an
alleged defect in at least one of the homes in each subset of homes
included within the scope of the extrapolated notice. Additionally, the
claimants must provide the address of each home tested and clearly
identify the subset of homes to which the pre-litigation notice
applies. In order to provide valid pre-litigation notice, claimants
must narrow the scope of their extrapolated notice. </p>
<p>They should
investigate and identify a subset of homes within the community that
has the purported defect. If they genuinely believe that every home in
the community may have the alleged defect, then the claimants should
test and verify the defect in at least one home from each subset of
homes in the community and extrapolate the percentage of homes within
each subset that they believe are likely to contain the defect. </p>
<p>The
court emphasized that the legislature intended NRS 40.645 to provide
Nevada contractors an opportunity to inspect and repair defects in the
homes they construct. To that end, a pre-litigation notice must contain
reasonable detail so that a contractor, who makes the business
decision, can decide whether to inspect and repair. The Court also
concluded that a claimant cannot utilize the phrase “to the extent
known” in NRS 40.645(2)(c) to justify withholding pertinent information
from a pre-litigation notice, and that NRS 40.645(4)(c) requires a
claimant to disclose the expert opinions and reports in its possession
that were used to prepare its pre-litigation notice.</p>